10839 N ELDORA AVE 91040

Certificate Information: 10839 N ELDORA AVE 91040

Application / Permit
20014-10000-02614
Plan Check / Job No.
B20LA11153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD AND INTERIOR REMODEL
Permit Issued
Issued on 4/16/2021
Issuing Office
Current Status
CofO Issued on 6/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 CRYSTEL MAALOUF
Corrections Issued 9/4/2020 CRYSTEL MAALOUF
Quality Review Completed 9/29/2020 WING SUEN
Building Plans Picked Up 9/30/2020 APPLICANT
Applicant returned to address corrections 1/7/2021 CRYSTEL MAALOUF
Plan Check Approved 3/25/2021 CRYSTEL MAALOUF
Issued 4/16/2021 APPLICANT
CofO in Progress 5/18/2022 MATTHEW NELSON
CofO Issued 6/13/2022 DANIEL ORRANTE
Permit Finaled 6/13/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/9/2020 BRIAN MILLER
Sewer availability Cleared 12/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 12/16/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 3/19/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/19/2021 GUILLERMO PETRA
GPI Written Notices Cleared 3/25/2021 WING SUEN

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/9/2021 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 7/21/2021 Approved MATTHEW NELSON
Drywall Nailing 8/2/2021 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 8/10/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/30/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 8/30/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 8/30/2021 Partial Inspection WILLIAM KUEHN
HVAC-Rough 8/30/2021 Approved WILLIAM KUEHN
Deputy Wood Construction 9/2/2021 Partial Approval MATTHEW NELSON
Insulation 9/10/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/10/2021 Approved MATTHEW NELSON
Insulation 9/13/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/13/2021 Approved MATTHEW NELSON
Drywall Nailing 9/21/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 11/30/2021 Approved MATTHEW NELSON
Final 11/30/2021 Corrections Issued MATTHEW NELSON
Green Building Final 11/30/2021 Corrections Issued MATTHEW NELSON
Green Building Rough 11/30/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 11/30/2021 Approved MATTHEW NELSON
Pre-Inspection 12/28/2021 Corrections Issued MATTHEW NELSON
Final 1/19/2022 Corrections Issued MATTHEW NELSON
Green Building Final 1/19/2022 Corrections Issued MATTHEW NELSON
Final 3/18/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Final 3/18/2022 Not Ready for Inspection MATTHEW NELSON
Final 3/25/2022 Not Ready for Inspection MATTHEW NELSON
Green Building Final 3/25/2022 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 5/17/2022 Approved MATTHEW NELSON
Final 5/17/2022 OK to Issue CofO MATTHEW NELSON
Green Building Final 5/17/2022 Approved MATTHEW NELSON
HVAC-Final 5/17/2022 Approved MATTHEW NELSON
PLUMBING-Final 5/17/2022 Approved MATTHEW NELSON