632 1/2 W ROMULO ST 90065

Certificate Information: 632 1/2 W ROMULO ST 90065

Application / Permit
20014-10000-02599
Plan Check / Job No.
B20LA11068
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE AND ADD 12'10x17' AT THE SIDE OF THE STRUCTURE TO CREATE ACCESSORY DWELLING UNIT; ALL WORK PER WFPP
Permit Issued
Issued on 1/20/2021
Issuing Office
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 GEORGE ALVAREZ
Corrections Issued 7/15/2020 GEORGE ALVAREZ
Plan Check Approved 1/8/2021 SINA KHOSRAVI
Issued 1/20/2021 APPLICANT
Building Plans Picked Up 1/25/2021 APPLICANT
CofO in Progress 2/2/2022 OSVALDO PARAMO
CofO in Progress 2/2/2022 OSVALDO PARAMO
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/4/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 8/27/2020 RENZ SORIANO
Address approval Cleared 10/6/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/6/2020 CECILIO NAVARRO
Sewer availability Cleared 10/6/2020 CECILIO NAVARRO
Supp. Use District POD/CDO/TDO Cleared 10/15/2020 ADRINEH MELKONIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 9/14/2021 Partial Approval ALAN MORELOS
Sewer 9/14/2021 Approved ALAN MORELOS
Excavation/Setback/Form/Re-Bar 9/16/2021 Corrections Issued COREY HUPP
Underground Mechanical 9/16/2021 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 9/20/2021 Conditional Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/24/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/20/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Approved OSVALDO PARAMO
HVAC-Rough 10/20/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 10/20/2021 Approved OSVALDO PARAMO
Wood Frame 10/20/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 11/3/2021 Approved OSVALDO PARAMO
Green Building Rough 11/3/2021 Approved OSVALDO PARAMO
Insulation 11/3/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/3/2021 Partial Approval OSVALDO PARAMO
Drywall Nailing 11/10/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/10/2021 Approved OSVALDO PARAMO
Final 1/27/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 1/27/2022 Approved OSVALDO PARAMO
Green Building Final 1/27/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 1/27/2022 Approved OSVALDO PARAMO
Final 2/1/2022 OK to Issue CofO OSVALDO PARAMO