3576 S WASATCH AVE 90066
Certificate Information: 3576 S WASATCH AVE 90066
- Application / Permit
- 20014-10000-02597
- Plan Check / Job No.
- B20LA11064
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2ND FLOOR ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c)-(d)
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | DANIEL YIP |
| Corrections Issued | 7/23/2020 | DANIEL YIP |
| Quality Review Completed | 8/14/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| Applicant returned to address corrections | 12/8/2020 | DANIEL YIP |
| Plan Check Approved | 4/15/2021 | DANIEL YIP |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 4/20/2022 | PATRICK QUALEY |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
| CofO Issued | 4/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/5/2020 | FREDDY GARCIA |
| Address approval | Cleared | 10/6/2020 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 10/30/2020 | NIKTA MOUSAVI |
| GPI Written Notices | Cleared | 12/8/2020 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 12/8/2020 | DANIEL YIP |
| Green Code | Cleared | 12/8/2020 | DANIEL YIP |
Contact Information
| Architect | Best,, Richard Allen; Lic. No.: C17334 | 1275 BEVERLY ESTATES DR. BEVERLY HILLS, CA 90210 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/28/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 8/12/2021 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 8/12/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 8/23/2021 | No Result Entered | System User |
| Wood Frame | 8/24/2021 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/17/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 9/17/2021 | Conditional Approval | ENRIQUE MIRELES |
| Wood Frame | 9/17/2021 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/20/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 9/20/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 9/20/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Wood Construction | 9/22/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 10/1/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/2/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/2/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 11/5/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/8/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Wood Frame | 11/16/2021 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 1/10/2022 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/10/2022 | Partial Approval | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 1/10/2022 | Approved | STEPHANIE SWANSON |
| Insulation | 1/19/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 2/7/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 2/7/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/10/2022 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/16/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/18/2022 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | PATRICK QUALEY |
| ELECTRICAL-Final | 4/4/2022 | Approved | PATRICK QUALEY |
| Final | 4/4/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Final | 4/4/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 4/4/2022 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | PATRICK QUALEY |
| Final | 4/20/2022 | OK to Issue CofO | PATRICK QUALEY |
| Green Building Final | 4/20/2022 | Approved | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Approved | PATRICK QUALEY |
| Service/Power Release | 4/20/2022 | Approved | PATRICK QUALEY |
| Smoke Detectors | 4/20/2022 | Approved | PATRICK QUALEY |