3814 S REDONDO BLVD 90008
Certificate Information: 3814 S REDONDO BLVD 90008
- Application / Permit
- 20014-10000-02581
- Plan Check / Job No.
- B20LA10969
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION AND CONVERT ATTIC TO HABITABLE AREA AND REMODEL DWELLING.
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/23/2020 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/31/2020 | TIEN JEN WANG |
| Applicant returned to address corrections | 1/29/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 4/1/2021 | MAHNAZ NOURHASHEMI |
| Issued | 4/5/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | ANTHONY EGSON |
| Permit Finaled | 1/3/2023 | DEROLD HAUFF |
| CofO Issued | 1/3/2023 | DEROLD HAUFF |
| Permit Finaled | 1/3/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 2/19/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 2/22/2021 | BRIAN MILLER |
| Low Impact Development | Cleared | 3/10/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/11/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 4/1/2021 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Golden Age Builders; Lic. No.: 1040171-B | 7494 SANTA MONICA BLVD 201 LOS ANGELES, CA 90046 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/7/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/24/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 6/28/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Corrections Issued | DAVID FEILER |
| Deputy Wood Construction | 7/8/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 11/17/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/17/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/12/2022 | Partial Inspection | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 1/12/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Rough | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| Insulation | 1/18/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/18/2022 | Corrections Issued | ANTHONY EGSON |
| Deputy Wood Construction | 1/19/2022 | Conditional Approval | ADAM ESCOTO |
| Insulation | 1/25/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/31/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 1/31/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/31/2022 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/9/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/9/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 2/9/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 2/25/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/25/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 2/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 3/2/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/16/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 8/23/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 8/23/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 8/23/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 8/23/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 8/23/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 8/23/2022 | Approved | ANTHONY EGSON |
| Final | 10/6/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/6/2022 | Approved | ANTHONY EGSON |
| Final | 10/19/2022 | OK to Issue CofO | ANTHONY EGSON |