8242 N TEESDALE AVE 91605

Certificate Information: 8242 N TEESDALE AVE 91605

Application / Permit
20014-10000-02578
Plan Check / Job No.
B20LA10955
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING 1 STORY RECREATION ROOM WITH ATTACHED GARAGE TO BE CONVERTED TO PROPOSED 2-STORY ADU WITH ATTACHED GARAGE.
Permit Issued
Issued on 9/20/2021
Issuing Office
Metro
Current Status
CofO Issued on 5/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/23/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 CRYSTEL MAALOUF
Corrections Issued 8/5/2020 CRYSTEL MAALOUF
Quality Review Completed 9/28/2020 WING SUEN
Applicant returned to address corrections 4/16/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 6/9/2021 CRYSTEL MAALOUF
Plan Check Approved 6/14/2021 CRYSTEL MAALOUF
Building Plans Picked Up 9/14/2021 APPLICANT
Issued 9/20/2021 APPLICANT
CofO in Progress 5/4/2023 GREGG CUMMINGS
CofO Issued 5/22/2023 MICHAEL SMITH
Permit Finaled 5/22/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/9/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/9/2020 LEE GUILBEAUX
Sewer availability Cleared 12/10/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/17/2020 LEE GUILBEAUX

Contact Information

Contractor Refinish Plus Inc; Lic. No.: 1050293-B 8133 PURITAN ST      DOWNEY, CA 90242
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2021 Corrections Issued DAVID MATSON
Deputy Drilled-In Anchors 10/12/2021 Conditional Approval GREGG CUMMINGS
Footing/Foundation/Slab 10/15/2021 Approved MATTHEW NELSON
Wood Frame 11/9/2021 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Partial Approval GREGG CUMMINGS
Deputy Drilled-In Anchors 11/23/2021 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 11/24/2021 Not Ready for Inspection WILLIAM WREN
Sewer 11/24/2021 Partial Approval WILLIAM WREN
Shower Pan 11/24/2021 Approved WILLIAM WREN
HVAC-Rough 12/3/2021 Partial Approval GREGG CUMMINGS
Sewer 12/3/2021 Approved GREGG CUMMINGS
ELECTRICAL-Rough 12/20/2021 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 12/20/2021 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 12/20/2021 Partial Approval GREGG CUMMINGS
Wood Frame 12/20/2021 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 1/19/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/26/2022 Corrections Issued GREGG CUMMINGS
HVAC-Rough 1/26/2022 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 1/26/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/26/2022 Corrections Issued GREGG CUMMINGS
Wood Frame 1/26/2022 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 3/17/2022 Not Ready for Inspection GREGG CUMMINGS
Insulation 3/17/2022 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 3/17/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 3/25/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 3/25/2022 Approved GREGG CUMMINGS
HVAC-Rough 3/25/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 3/25/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 4/1/2022 Approved GREGG CUMMINGS
Green Building Rough 4/1/2022 Approved GREGG CUMMINGS
Insulation 4/1/2022 Corrections Issued GREGG CUMMINGS
MERV13>=Rough 4/1/2022 Approved GREGG CUMMINGS
Insulation 4/22/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/3/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/5/2022 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 7/2/2022 Approved ASHLEY THOMPSON
Shower Pan 7/2/2022 Approved ASHLEY THOMPSON
Service/Power Release 10/7/2022 Not Ready for Inspection GREGG CUMMINGS
Final 10/17/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 10/17/2022 Approved GREGG CUMMINGS
MERV13>=Final 10/17/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 10/17/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 4/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 4/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 4/24/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 4/24/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/3/2023 Approved GREGG CUMMINGS
Final 5/3/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 5/3/2023 Approved GREGG CUMMINGS
PLUMBING-Final 5/3/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved GREGG CUMMINGS