446 S SYCAMORE AVE 90036
Certificate Information: 446 S SYCAMORE AVE 90036
- Application / Permit
- 20014-10000-02561
- Plan Check / Job No.
- B20LA10897
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert exisiting 2 car garage to an ADU with a second floor addition.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- Issued on 11/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | SAMUEL GONZALEZ |
| Corrections Issued | 7/14/2020 | SAMUEL GONZALEZ |
| Quality Review Completed | 7/16/2020 | STANLEY RAAP |
| Plan Check Approved | 10/21/2021 | SAMUEL GONZALEZ |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/5/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/30/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 12/9/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 6/22/2021 | RIDWAN HARDY |
| Address approval | Cleared | 9/14/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 9/23/2021 | NAZILA NOORIFAR |
Contact Information
| Contractor | Engine Construction Inc; Lic. No.: 1024143-B | 13365 W WASHINGTON BVLD APT 305 LOS ANGELES, CA 90066 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/16/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 11/17/2021 | Corrections Issued | ARTHUR SARGSYAN |
| METHANE-Barrier | 11/17/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 11/17/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/17/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 11/19/2021 | Partial Approval | ARTHUR SARGSYAN |
| Pre-Inspection | 11/22/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 12/3/2021 | Partial Approval | ADAM ESCOTO |
| Deputy Wood Construction | 12/13/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 12/22/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 12/22/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 12/22/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/30/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/6/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/6/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 1/11/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 1/26/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 2/15/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/22/2022 | SGSOV Not Ready | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 3/1/2022 | Approved | ARTHUR SARGSYAN |