1107 E 114TH ST 90059
Certificate Information: 1107 E 114TH ST 90059
- Application / Permit
- 20014-10000-02559
- Plan Check / Job No.
- B20LA10873
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION AND REMODEL OF 1-STORY TO (E) SFD. REMODEL (E) INTERIOR DRYWALL, REPLACE DOORS, RELOCATE KITCHEN. CONVERT TO 3 BEDROOM + 2 BATHROOMS.
- Permit Issued
- Issued on 8/20/2020
- Issuing Office
- Current Status
- CofO Issued on 4/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2020 | JESSE JIMENEZ |
| Corrections Issued | 7/7/2020 | JESSE JIMENEZ |
| Plan Check Approved | 8/5/2020 | RICARDO RAMIREZ |
| Issued | 8/20/2020 | APPLICANT |
| Building Plans Picked Up | 8/21/2020 | APPLICANT |
| CofO in Progress | 3/1/2021 | EUGENE CASSIDY |
| Permit Finaled | 4/8/2021 | DEROLD HAUFF |
| CofO Issued | 4/8/2021 | DEROLD HAUFF |
| Permit Finaled | 4/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | JEANIE LAM |
Contact Information
| Contractor | Moreno Chris; Lic. No.: 973501-B | 1158 W 126TH STREET LOS ANGELES, CA 90044 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/31/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 9/3/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/16/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/21/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Approval | EUGENE CASSIDY |
| Insulation | 9/21/2020 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 9/25/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 9/29/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/6/2020 | Conditional Approval | EUGENE CASSIDY |
| Green Building Rough | 10/6/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/7/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 10/14/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 10/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/20/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 10/20/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/20/2020 | Approved | EUGENE CASSIDY |
| Insulation | 10/26/2020 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 10/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 10/29/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/5/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/22/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 1/29/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 2/22/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/22/2021 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 2/22/2021 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/1/2021 | Approved | EUGENE CASSIDY |
| Final | 3/1/2021 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 3/1/2021 | Approved | EUGENE CASSIDY |
| HVAC-Final | 3/1/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/1/2021 | Approved | EUGENE CASSIDY |
| Service/Power Release | 3/1/2021 | Approved | EUGENE CASSIDY |