11887 W JUNIETTE ST 90230

Certificate Information: 11887 W JUNIETTE ST 90230

Application / Permit
20014-10000-02558
Plan Check / Job No.
B20LA10864
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
-REMODEL OF (E) RESIDENCE CONSISTING OF NEW KITCHEN & BATHROOMS -ADDITION OF 59 SF OF SPACE & NEW TRELLIS
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
CofO Issued on 2/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/23/2020 MONICA RAMIREZ
Corrections Issued 6/23/2020 MONICA RAMIREZ
Applicant returned to address corrections 7/30/2020 LUKE GONZALES
Building Plans Picked Up 8/11/2020 APPLICANT
Applicant returned to address corrections 9/16/2020 LAWRENCE QUIRANTE
Plan Check Approved 9/17/2020 LAWRENCE QUIRANTE
Issued 12/14/2020 APPLICANT
CofO in Progress 2/1/2022 ENRIQUE MIRELES
CofO in Progress 2/1/2022 ENRIQUE MIRELES
Permit Finaled 2/8/2022 DANIEL ORRANTE
Permit Finaled 2/8/2022 DANIEL ORRANTE
CofO Issued 2/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/9/2020 CATHERINE ADROVER
Roof/Waste drainage to street Cleared 9/11/2020 DINAH GARIN

Contact Information

Contractor Expo Home Design & Remodeling Inc; Lic. No.: 911716-B 12725 VENTURA BLVD #D      STUDIO CITY, CA 91604
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/12/2021 Corrections Issued JOHNNY MIRANDA
METHANE-Barrier 1/12/2021 Approved JOHNNY MIRANDA
METHANE-Subgrade 1/12/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 1/15/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/14/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 4/14/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 4/14/2021 Not Ready for Inspection JOHNNY MIRANDA
MERV13>=Rough 4/14/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 4/14/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 4/14/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/19/2021 Corrections Issued ENRIQUE MIRELES
Insulation 4/22/2021 Conditional Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 4/26/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/26/2021 Corrections Issued JUAN VALENZUELA
Green Building Rough 4/26/2021 Approved JUAN VALENZUELA
MERV13>=Rough 4/26/2021 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 4/26/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 4/29/2021 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 4/29/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 4/30/2021 Approved JUAN VALENZUELA
MERV13>=Rough 4/30/2021 Approved JUAN VALENZUELA
Shower Pan 4/30/2021 Corrections Issued JUAN VALENZUELA
Drywall Nailing 5/6/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/6/2021 Approved ENRIQUE MIRELES
Shower Pan 5/6/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/11/2021 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 5/17/2021 Partial Approval PIERRE VEGA
Final 10/20/2021 Corrections Issued DAVID FEILER
Green Building Final 10/20/2021 Not Ready for Inspection DAVID FEILER
MERV13>=Final 10/20/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 10/20/2021 Not Ready for Inspection DAVID FEILER
Final 1/6/2022 Not Ready for Inspection DAVID FEILER
Green Building Final 1/6/2022 Not Ready for Inspection DAVID FEILER
MERV13>=Final 1/6/2022 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 1/6/2022 Not Ready for Inspection DAVID FEILER
Final 1/20/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/20/2022 Approved ENRIQUE MIRELES
HVAC-Final 1/20/2022 Not Ready for Inspection ENRIQUE MIRELES
MERV13>=Final 1/20/2022 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 1/20/2022 Approved ENRIQUE MIRELES
HVAC-Final 1/27/2022 Not Ready for Inspection DAVID FEILER
Final 2/1/2022 OK to Issue CofO ENRIQUE MIRELES
MERV13>=Final 2/1/2022 Approved ENRIQUE MIRELES