12675 N ADELPHIA AVE 91340

Certificate Information: 12675 N ADELPHIA AVE 91340

Application / Permit
20014-10000-02551
Plan Check / Job No.
B20LA10823
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW 2-STORY DETACHED ADU WITH ROOF DECK PER LAMC 12.22 A.33(c)AND (d).
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 12/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/19/2020 APPLICANT
Assigned to Plan Check Engineer 6/23/2020 CRISTINA SALAZAR
Corrections Issued 6/23/2020 CRISTINA SALAZAR
Quality Review Completed 7/9/2020 STANLEY RAAP
Applicant returned to address corrections 4/23/2021 CRISTINA SALAZAR
Applicant returned to address corrections 4/27/2021 CRISTINA SALAZAR
Applicant returned to address corrections 5/21/2021 CRISTINA SALAZAR
Applicant returned to address corrections 6/9/2021 CRISTINA SALAZAR
Applicant returned to address corrections 7/12/2021 CRISTINA SALAZAR
Applicant returned to address corrections 8/5/2021 CRISTINA SALAZAR
Plan Check Approved 8/16/2021 CRISTINA SALAZAR
Issued 8/16/2021 APPLICANT
Building Plans Picked Up 8/18/2021 APPLICANT
CofO in Progress 10/29/2025 KEVIN BERBERYAN
Permit Finaled 12/3/2025 RUBEN SALAS
CofO Issued 12/3/2025 RUBEN SALAS
Permit Finaled 12/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/27/2020 ADRIAN CASTRO
Sewer availability Cleared 8/27/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/22/2020 ADRIAN CASTRO
Low Impact Development Cleared 4/8/2021 MITESH PATEL
Green Code Cleared 7/12/2021 CRISTINA SALAZAR
Roof/Waste drainage to street Cleared 8/3/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2021 Approved JOHN HAYES
Gas Test 11/5/2021 Partial Approval JOHN HAYES
PLUMBING-Rough 11/5/2021 Not Ready for Inspection JOHN HAYES
Sewer 11/5/2021 Partial Approval JOHN HAYES
Footing/Foundation/Slab 6/21/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/8/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 9/2/2022 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval KEVIN BERBERYAN
Insulation 7/25/2024 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 7/25/2024 Partial Approval KEVIN BERBERYAN
BUILDING-Rough-Frame 8/7/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 8/7/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Rough 8/7/2024 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 8/7/2024 Approved KEVIN BERBERYAN
Wood Frame 10/1/2024 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 10/17/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/18/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/18/2024 Corrections Issued KEVIN BERBERYAN
Deck 10/30/2024 Partial Approval KEVIN BERBERYAN
Insulation 10/30/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 10/30/2024 Approved KEVIN BERBERYAN
Drywall Nailing 11/21/2024 Approved KEVIN BERBERYAN
Green Building Rough 11/21/2024 Approved KEVIN BERBERYAN
HVAC-Rough 11/21/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/21/2024 Approved KEVIN BERBERYAN
Shower Pan 11/21/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 12/4/2024 Approved KEVIN BERBERYAN
Deputy Steel/Welding 4/1/2025 Conditional Approval RAUL OLAGI
Deputy Steel/Welding 4/29/2025 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 5/21/2025 Approved KEVIN BERBERYAN
Final 5/21/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 5/21/2025 Approved KEVIN BERBERYAN
MERV13>=Final 5/21/2025 Approved KEVIN BERBERYAN
MERV13>=Rough 5/21/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Not Ready KEVIN BERBERYAN
Service/Power Release 5/21/2025 Not Required KEVIN BERBERYAN
Smoke Detectors 5/21/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 9/18/2025 Approved KEVIN BERBERYAN
Final 9/18/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/18/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/18/2025 Approved KEVIN BERBERYAN
Final 10/29/2025 OK to Issue CofO KEVIN BERBERYAN