6070 1/2 W COMEY AVE 90034

Certificate Information: 6070 1/2 W COMEY AVE 90034

Application / Permit
20014-10000-02538
Plan Check / Job No.
B20LA10753
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 2 STORY ADU ADDITION TO (E) DETACHED GARAGE per Ordinance 186,481 [LAMC 12.22 A.33(b)(1)]
Permit Issued
Issued on 6/14/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 ARMEN JIVALAGIAN
Corrections Issued 7/14/2020 ARMEN JIVALAGIAN
Quality Review Completed 7/16/2020 CHAD DOI
Building Plans Picked Up 9/1/2020 APPLICANT
Applicant returned to address corrections 4/13/2021 ARMEN JIVALAGIAN
Plan Check Approved 5/18/2021 ARMEN JIVALAGIAN
Issued 6/14/2021 APPLICANT
CofO in Progress 8/8/2022 EVAN COOPER
Permit Finaled 8/26/2022 DANIEL ORRANTE
CofO Issued 8/26/2022 DANIEL ORRANTE
Permit Finaled 8/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/7/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/14/2020 JEANIE LAM
Sewer availability Cleared 10/14/2020 JEANIE LAM
Low Impact Development Cleared 1/26/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/22/2021 JEANIE LAM
Construction near power lines Cleared 4/21/2021 RIDWAN HARDY
Construction within easement Cleared 4/21/2021 RIDWAN HARDY

Contact Information

Architect Kim,, Nam H; Lic. No.: C30825 1832 SANTA RENA DRIVE      RANCHO PALOS VERDES, CA 90275
Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor G S Tingling; Lic. No.: 952884-B 7725 GATEWAY   UNIT 2253    IRVINE, CA 92618

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/17/2021 Partial Approval EVAN COOPER
Sewer 6/17/2021 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 8/12/2021 Approved EVAN COOPER
Footing/Foundation/Slab 8/17/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 8/30/2021 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 9/14/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/31/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/31/2022 Approved EVAN COOPER
Green Building Rough 1/31/2022 Not Ready for Inspection EVAN COOPER
MERV13>=Rough 1/31/2022 Approved EVAN COOPER
PLUMBING-Rough 1/31/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 2/23/2022 Approved EVAN COOPER
Green Building Rough 2/23/2022 Approved EVAN COOPER
HVAC-Rough 2/23/2022 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 2/23/2022 Approved EVAN COOPER
PLUMBING-Rough 2/23/2022 Approved EVAN COOPER
Insulation 3/15/2022 Corrections Issued EVAN COOPER
Drywall Nailing 3/31/2022 Approved EVAN COOPER
Insulation 3/31/2022 Approved EVAN COOPER
ELECTRICAL-Rough 6/23/2022 Approved EVAN COOPER
Final 7/6/2022 Corrections Issued EVAN COOPER
Final 7/11/2022 Corrections Issued EVAN COOPER
Green Building Final 7/11/2022 Corrections Issued EVAN COOPER
MERV13>=Final 7/11/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/11/2022 Corrections Issued EVAN COOPER
Smoke Detectors 7/11/2022 Corrections Issued EVAN COOPER
ELECTRICAL-Final 7/15/2022 Corrections Issued EVAN COOPER
Final 7/15/2022 Corrections Issued EVAN COOPER
Green Building Final 7/15/2022 Approved EVAN COOPER
MERV13>=Final 7/15/2022 Corrections Issued EVAN COOPER
PLUMBING-Final 7/15/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 7/15/2022 Corrections Issued EVAN COOPER
Final 7/20/2022 Corrections Issued EVAN COOPER
MERV13>=Final 7/20/2022 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 7/20/2022 Approved EVAN COOPER
Final 8/1/2022 Corrections Issued EVAN COOPER
MERV13>=Final 8/1/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved EVAN COOPER
Service/Power Release 8/2/2022 Approved EVAN COOPER
Final 8/8/2022 OK to Issue CofO EVAN COOPER
Service/Power Release 8/8/2022 Approved EVAN COOPER