2438 N HAVERHILL DR 90065

Certificate Information: 2438 N HAVERHILL DR 90065

Application / Permit
20014-10000-02489
Plan Check / Job No.
B20LA10597
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BATHROOM ADDITION TO REAR OF (E) SFD.
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 LAWRENCE QUIRANTE
Corrections Issued 7/13/2020 LAWRENCE QUIRANTE
Quality Review Completed 7/16/2020 FELIX FIGUEROA
Building Plans Picked Up 7/23/2020 APPLICANT
Applicant returned to address corrections 8/31/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/6/2020 LAWRENCE QUIRANTE
Plan Check Approved 10/9/2020 LAWRENCE QUIRANTE
Issued 9/3/2021 APPLICANT
CofO in Progress 4/18/2022 HAMIK HARTOUNIAN
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/26/2020 ROBERT HUGHES
Specific Plan Cleared 8/20/2020 NASHYA JENSEN
Eng Process Fee Ord 176,300 Cleared 8/21/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 8/21/2020 JEANIE LAM
Sewer availability Cleared 8/21/2020 JEANIE LAM

Contact Information

Contractor U S Home Developers Inc; Lic. No.: 947505-B 19737 VENTURA BLVD #310A      WOODLAND HILLS, CA 91367
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/17/2021 No Access for Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 9/22/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/21/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/1/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/1/2021 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/1/2021 No Access for Inspection HAMIK HARTOUNIAN
Green Building Rough 12/1/2021 No Access for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 12/1/2021 No Access for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/11/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 1/11/2022 Approved THOMAS LOGRASSO
Green Building Rough 1/11/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 1/11/2022 Corrections Issued THOMAS LOGRASSO
Deputy Drilled-In Anchors 1/12/2022 Conditional Approval THOMAS LOGRASSO
Deputy Wood Construction 1/13/2022 Conditional Approval OSVALDO PARAMO
BUILDING-Rough-Frame 1/14/2022 Not Ready for Inspection LILIANA PORTILLO
Deputy Wood Construction 1/14/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/14/2022 Approved LILIANA PORTILLO
Green Building Rough 1/14/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 1/14/2022 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 2/8/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/17/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 2/17/2022 Approved HAMIK HARTOUNIAN
Insulation 2/28/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 2/28/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 3/10/2022 Approved HAMIK HARTOUNIAN
Shower Pan 3/15/2022 Conditional Approval HAMIK HARTOUNIAN
Final 4/13/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 4/13/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/13/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 4/13/2022 Approved HAMIK HARTOUNIAN