4625-4627 S 5TH AVE 90043
Certificate Information: 4625-4627 S 5TH AVE 90043
- Application / Permit
- 20014-10000-02485
- Plan Check / Job No.
- B20LA10565
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ADDITION TO 1ST AND 2ND FLOOR OF AN EXISTING 2 STORY DUPLEX 1 OF 2
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- Issued on 12/8/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | VU NGUYEN |
| Corrections Issued | 7/16/2020 | VU NGUYEN |
| Quality Review Completed | 7/21/2020 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/1/2020 | VU NGUYEN |
| Plan Check Approved | 12/1/2020 | VU NGUYEN |
| Issued | 12/8/2020 | APPLICANT |
| Building Plans Picked Up | 12/11/2020 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/17/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2020 | WALLIE JONG |
| Sewer availability | Cleared | 8/18/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2021 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 3/19/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 3/19/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/19/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 4/9/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/28/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 5/28/2021 | Partial Approval | DAVID FEILER |
| Gas Test | 6/7/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 6/7/2021 | Approved | FREDDIE RIVERA |
| Gas Test | 6/10/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 6/10/2021 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 6/14/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 6/24/2021 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 6/28/2021 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 6/28/2021 | Partial Inspection | DAVID FEILER |
| Insulation | 7/2/2021 | Corrections Issued | ALFREDO BALANDRA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Approved | FREDDIE RIVERA |
| Insulation | 7/7/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 7/13/2021 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/26/2021 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 7/30/2021 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | ADAM ESCOTO |
| Final | 10/14/2021 | Not Ready for Inspection | ADAM ESCOTO |
| Footing/Foundation/Slab | 10/14/2021 | Approved | ADAM ESCOTO |
| Green Building Final | 10/14/2021 | Approved | ADAM ESCOTO |
| Green Building Rough | 10/14/2021 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | ADAM ESCOTO |
| Smoke Detectors | 10/14/2021 | Corrections Issued | ADAM ESCOTO |
| Final | 11/8/2021 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 11/8/2021 | Approved | ANTHONY EGSON |
| Final | 11/15/2021 | Corrections Issued | ANTHONY EGSON |
| Final | 2/4/2022 | Conditional Approval | ANTHONY EGSON |