833 W 112TH ST 90044

Certificate Information: 833 W 112TH ST 90044

Application / Permit
20014-10000-02467
Plan Check / Job No.
B20LA10477
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BEDROOM ADDITION TO EXISTING SFD PER WFFP
Permit Issued
Issued on 10/13/2020
Issuing Office
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/16/2020 FERNANDO FLORES
Corrections Issued 6/16/2020 FERNANDO FLORES
Applicant returned to address corrections 7/16/2020 STARR CHEN
Applicant returned to address corrections 7/23/2020 AUNG SOE
Applicant returned to address corrections 8/24/2020 CRISTINA SALAZAR
Plan Check Approved 10/2/2020 AUNG SOE
Issued 10/13/2020 APPLICANT
Building Plans Picked Up 10/19/2020 APPLICANT
CofO in Progress 8/27/2021 EUGENE CASSIDY
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/11/2020 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 8/13/2020 JAMES KHO
Tenant Habitability Plan Cleared 9/28/2020 PHILLIP MUNGUIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/5/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 4/5/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 4/30/2021 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/30/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 5/5/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval EUGENE CASSIDY
Deputy Drilled-In Anchors 5/7/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Approved EUGENE CASSIDY
Insulation 5/11/2021 Approved EUGENE CASSIDY
Wood Frame 6/7/2021 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 6/18/2021 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 6/23/2021 Approved RICHARD STEINBACH
HVAC-Rough 6/23/2021 Approved RICHARD STEINBACH
Insulation 7/1/2021 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 7/1/2021 Partial Approval SABAS ALONSO
Drywall Nailing 7/7/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/4/2021 Approved EUGENE CASSIDY
Final 8/4/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 8/4/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/4/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/4/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 8/4/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 8/26/2021 Approved EUGENE CASSIDY
Final 8/26/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/26/2021 Approved EUGENE CASSIDY
HVAC-Final 8/26/2021 Approved EUGENE CASSIDY
PLUMBING-Final 8/26/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/26/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 8/26/2021 Approved EUGENE CASSIDY
Smoke Detectors 8/26/2021 Approved EUGENE CASSIDY