12506 W GILMORE AVE 90066

Certificate Information: 12506 W GILMORE AVE 90066

Application / Permit
20014-10000-02466
Plan Check / Job No.
B20LA10471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO AN EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/16/2020
Issuing Office
Current Status
Issued on 10/16/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2020 APPLICANT
Assigned to Plan Check Engineer 7/10/2020 MONICA RAMIREZ
Corrections Issued 7/15/2020 MONICA RAMIREZ
Quality Review Completed 7/16/2020 STANLEY RAAP
Building Plans Picked Up 7/23/2020 APPLICANT
Applicant returned to address corrections 8/13/2020 MONICA RAMIREZ
Plan Check Approved 10/16/2020 MONICA RAMIREZ
Issued 10/16/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/30/2020 KATHLEEN LEE
Roof/Waste drainage to street Cleared 8/7/2020 KATHLEEN LEE
Specific Plan Cleared 8/17/2020 ANNA VIDAL
Specific Plan Cleared 8/17/2020 VALERIA CEJA

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: C28865 12240 VENICE BLVD SUITE 25      LOS ANGELES, CA 90066
Contractor Silva Design Construction Inc; Lic. No.: 956083-B 1659 N LAKE AVE #6      PASADENA, CA 91104
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/23/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 12/8/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 12/8/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 12/8/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 12/9/2020 Approved JOHNNY MIRANDA
HVAC-Rough 12/9/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 12/9/2020 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 12/14/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Approved JOHNNY MIRANDA
Insulation 12/16/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/16/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 12/18/2020 Approved JOHNNY MIRANDA
Drywall Nailing 12/18/2020 Approved JOHNNY MIRANDA
Service/Power Release 12/18/2020 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 2/3/2021 Approved DAVID HEINE
Sewer 2/4/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 5/7/2021 SGSOV Not Ready ENRIQUE MIRELES
Final 5/14/2021 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 5/14/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 5/14/2021 Corrections Issued BRENDAN LOONEY
Final 5/20/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 5/20/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 5/20/2021 Approved ENRIQUE MIRELES
Final 6/4/2021 Corrections Issued ENRIQUE MIRELES
Verify Rec and Parks Fee Memo 6/7/2021 No Access for Inspection JOHNNY MIRANDA
Service/Power Release 8/31/2021 Approved ENRIQUE MIRELES
Final 9/1/2021 Corrections Issued JOHNNY MIRANDA