1841 S ORANGE GROVE AVE 90019
Certificate Information: 1841 S ORANGE GROVE AVE 90019
- Application / Permit
- 20014-10000-02454
- Plan Check / Job No.
- B20LA10419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SINGLE STORY ADDITION TO REAR OF (E) ONE STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/6/2020
- Issuing Office
- Current Status
- Issued on 10/6/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2020 | ALBERT SERVIN |
| Corrections Issued | 7/15/2020 | GARO TELMI |
| Quality Review Completed | 7/20/2020 | CHAD DOI |
| Applicant returned to address corrections | 8/27/2020 | GARO TELMI |
| Applicant returned to address corrections | 9/2/2020 | GARO TELMI |
| Applicant returned to address corrections | 9/16/2020 | GARO TELMI |
| Plan Check Approved | 9/25/2020 | GARO TELMI |
| Issued | 10/6/2020 | APPLICANT |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/21/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 9/22/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | AVALYN KAMACHI |
| Green Code | Cleared | 9/25/2020 | GARO TELMI |
Contact Information
| Architect | Zubick,, Anthony Philip; Lic. No.: C19924 | P O BOX 931810 LOS ANGELES, CA 90093 |
| Contractor | G M E Development; Lic. No.: 917664-B | 2731 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 10/21/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 10/21/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 11/19/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 11/19/2020 | Approved | DAVID CHAN |
| Green Building Rough | 11/19/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 11/19/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 11/19/2020 | Approved | DAVID CHAN |
| Insulation | 11/25/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/25/2020 | Partial Approval | DAVID CHAN |
| Drywall Nailing | 12/2/2020 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 12/15/2020 | Approved | RICHARD STEINBACH |
| Final | 4/7/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/7/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 4/7/2021 | Approved | STUART CHAPMAN |
| Final | 4/12/2021 | Conditional Approval | STUART CHAPMAN |
| Service/Power Release | 4/12/2021 | Approved | STUART CHAPMAN |