6209 E ROY ST 90042

Certificate Information: 6209 E ROY ST 90042

Application / Permit
20014-10000-02443
Plan Check / Job No.
B20LA10325
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING GARAGE WITH ADDITION TO ACCESSORY DWELLING UNIT WITH STORAGE
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 6/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2020 APPLICANT
Assigned to Plan Check Engineer 6/15/2020 ADAM HEGAZI
Corrections Issued 6/16/2020 ADAM HEGAZI
Applicant returned to address corrections 8/18/2020 ZAW HAN
Plan Check Approved 1/11/2021 FERNANDO FLORES
Issued 2/4/2021 APPLICANT
Building Plans Picked Up 3/1/2021 APPLICANT
CofO in Progress 2/22/2022 COREY HUPP
CofO Issued 6/8/2022 DEROLD HAUFF
Permit Finaled 6/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/22/2020 PATRICK MISCHLICH
Address approval Cleared 8/10/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/24/2020 RENZ SORIANO
BHO/Hillside ordinance Cleared 8/26/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/26/2020 RENZ SORIANO
Sewer availability Cleared 8/26/2020 RENZ SORIANO
Construction near power lines Cleared 12/17/2020 RIDWAN HARDY

Contact Information

Architect Christopher,, William Robert; Lic. No.: C11333 732 N GARDNER      LOS ANGELES, CA 90046
Contractor Cornerstone Construction And Design; Lic. No.: 775449-B 4910 MT ROYAL DRIVE      LOS ANGELES, CA 90041
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2021 Not Ready for Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 3/22/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/8/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/8/2021 Not Ready for Inspection CRAIG VAUGHAN
Verify Sprinkler Sign Off 4/8/2021 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 4/13/2021 Partial Approval RUBEN SALAS
Interior/Exterior Lathing 4/27/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 5/18/2021 Partial Approval COREY HUPP
ELECTRICAL-Rough 5/18/2021 Not Ready for Inspection COREY HUPP
Underground Mechanical 5/18/2021 Corrections Issued COREY HUPP
Underground Mechanical 5/26/2021 Not Ready for Inspection COREY HUPP
Underground Mechanical 6/2/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 6/8/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/18/2021 Approved COREY HUPP
ELECTRICAL-Rough 6/18/2021 Approved COREY HUPP
HVAC-Rough 6/18/2021 Approved COREY HUPP
PLUMBING-Rough 6/18/2021 Approved COREY HUPP
Shower Pan 6/23/2021 Approved COREY HUPP
Interior/Exterior Lathing 6/25/2021 Partial Approval COREY HUPP
Interior/Exterior Lathing 6/30/2021 Conditional Approval COREY HUPP
Insulation 7/12/2021 Conditional Approval COREY HUPP
Drywall Nailing 7/16/2021 Approved JUSTIN HAWLEY
Final 10/8/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 10/8/2021 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 10/8/2021 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 1/18/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 1/18/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/18/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/7/2022 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 2/7/2022 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Not Ready COREY HUPP
Smoke Detectors 2/7/2022 Not Ready for Inspection COREY HUPP
Final 2/15/2022 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready COREY HUPP
Smoke Detectors 2/15/2022 Approved COREY HUPP
Final 2/22/2022 OK to Issue CofO COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/22/2022 SGSOV Approved COREY HUPP