1021 W 74TH ST 90044
Certificate Information: 1021 W 74TH ST 90044
- Application / Permit
- 20014-10000-02433
- Plan Check / Job No.
- B20LA10274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE INTO AN ADU WITH ADDITION.
- Permit Issued
- Issued on 12/2/2020
- Issuing Office
- Current Status
- Issued on 12/2/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2020 | MONICA RAMIREZ |
| Corrections Issued | 6/15/2020 | MONICA RAMIREZ |
| Plan Check Approved | 11/12/2020 | SAMUEL GONZALEZ |
| Issued | 12/2/2020 | APPLICANT |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2020 | WALLIE JONG |
| Sewer availability | Cleared | 7/1/2020 | WALLIE JONG |
| Construction near power lines | Cleared | 9/23/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Silva P Construction Inc; Lic. No.: 1061045-B | 619 BUCKEYE STREET APT C PASADENA, CA 91104 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/23/2020 | Not Ready for Inspection | COREY HUPP |
| Underground Mechanical | 12/23/2020 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Sewer | 12/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 12/31/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/31/2020 | Approved | STUART CHAPMAN |
| Sewer | 12/31/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/16/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 2/16/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 2/16/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 2/16/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 2/16/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/8/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 3/8/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/8/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 3/8/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | DAVID FEILER |
| Insulation | 3/22/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/22/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 3/22/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 3/31/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 4/8/2021 | Not Ready for Inspection | RUBEN SALAS |
| Shower Pan | 5/19/2021 | Approved | WILLIAM WREN |
| Final | 6/11/2021 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/11/2021 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 6/11/2021 | Approved | FREDDIE RIVERA |
| Final | 10/1/2021 | Partial Approval | HORACE FULTZ |
| Service/Power Release | 1/4/2022 | Approved | HORACE FULTZ |