1021 W 74TH ST 90044

Certificate Information: 1021 W 74TH ST 90044

Application / Permit
20014-10000-02433
Plan Check / Job No.
B20LA10274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2-CAR GARAGE INTO AN ADU WITH ADDITION.
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
Issued on 12/2/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/12/2020 MONICA RAMIREZ
Corrections Issued 6/15/2020 MONICA RAMIREZ
Plan Check Approved 11/12/2020 SAMUEL GONZALEZ
Issued 12/2/2020 APPLICANT
Building Plans Picked Up 12/14/2020 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/30/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/1/2020 WALLIE JONG
Sewer availability Cleared 7/1/2020 WALLIE JONG
Construction near power lines Cleared 9/23/2020 RIDWAN HARDY

Contact Information

Contractor Silva P Construction Inc; Lic. No.: 1061045-B 619 BUCKEYE STREET APT C      PASADENA, CA 91104

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/23/2020 Not Ready for Inspection COREY HUPP
Underground Mechanical 12/23/2020 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 12/29/2020 Corrections Issued EUGENE CASSIDY
Sewer 12/29/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/31/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/31/2020 Approved STUART CHAPMAN
Sewer 12/31/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 2/16/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/16/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Partial Approval DAVID FEILER
HVAC-Rough 2/16/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 2/16/2021 Not Ready for Inspection DAVID FEILER
Wood Frame 2/16/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 3/8/2021 Partial Approval DAVID FEILER
Green Building Rough 3/8/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/8/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 3/8/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 3/22/2021 Approved DAVID FEILER
Insulation 3/22/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/22/2021 Partial Approval DAVID FEILER
PLUMBING-Rough 3/22/2021 Approved DAVID FEILER
Drywall Nailing 3/31/2021 Approved FREDDIE RIVERA
Drywall Nailing 4/8/2021 Not Ready for Inspection RUBEN SALAS
Shower Pan 5/19/2021 Approved WILLIAM WREN
Final 6/11/2021 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/11/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 6/11/2021 Approved FREDDIE RIVERA
Final 10/1/2021 Partial Approval HORACE FULTZ
Service/Power Release 1/4/2022 Approved HORACE FULTZ