1000 N NAPOLI DR 90272
Certificate Information: 1000 N NAPOLI DR 90272
- Application / Permit
- 20014-10000-02422
- Plan Check / Job No.
- B20LA10231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 (N) TRELLIS STRUCTURE ON LOT W/ (E) SFD
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Current Status
- CofO Issued on 2/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 7/28/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/5/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 8/11/2020 | APPLICANT |
| Plan Check Approved | 10/22/2020 | SERGIO GUTIERREZ |
| Issued | 10/30/2020 | APPLICANT |
| CofO in Progress | 10/3/2022 | KEVIN SARGSYAN |
| No Progress | 2/7/2023 | KENNETH NAGLE |
| CofO in Progress | 2/15/2023 | KENNETH NAGLE |
| Permit Finaled | 2/15/2023 | DANIEL ORRANTE |
| CofO Issued | 2/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/22/2020 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 10/22/2020 | SERGIO GUTIERREZ |
Contact Information
| Architect | Kelly,, Michael Kip; Lic. No.: C20478 | 752-K WILLOW STREET LEBANON, PA 17046 |
| Contractor | Benson Design & Build Inc Dba Dana Benson Construction; Lic. No.: 841251-B | 31826 VILLAGE CENTER RD STE G WESTLAKE VILLAGE, CA 91361 |
| Engineer | Ford,, Christina Parker; Lic. No.: C87469 | 1031 LEAVENWORTH ST 1 SAN FRANCISCO, CA 94109 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2020 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | KEVIN SARGSYAN |
| Final | 9/8/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 9/8/2022 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 9/8/2022 | Approved | KEVIN SARGSYAN |
| Smoke Detectors | 9/8/2022 | Approved | KEVIN SARGSYAN |
| Final | 9/29/2022 | Corrections Issued | KEVIN SARGSYAN |
| Final | 10/3/2022 | OK to Issue CofO | KEVIN SARGSYAN |