2291 N CHELAN DR 90068

Certificate Information: 2291 N CHELAN DR 90068

Application / Permit
20014-10000-02397
Plan Check / Job No.
B20LA10114
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO 2-STORY (E) SFD NEW ROOF TOP DECK AND EXTERIOR STAIRS FOR ACCESS NEW TRELLIS ROOF ABOVE ROOF TOP DECK
Permit Issued
Issued on 11/10/2021
Issuing Office
Current Status
CofO Issued on 10/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2020 APPLICANT
Assigned to Plan Check Engineer 7/1/2020 CARLOS MONTES
Corrections Issued 7/9/2020 CARLOS MONTES
Quality Review Completed 8/10/2020 PRANITA SHAH
Applicant returned to address corrections 9/29/2020 CARLOS MONTES
Plan Check Approved 1/27/2021 CARLOS MONTES
No Progress 10/20/2021 CARLOS MONTES
Plan Check Approved 10/20/2021 CARLOS MONTES
Issued 11/10/2021 APPLICANT
Building Plans Picked Up 11/16/2021 APPLICANT
CofO in Progress 8/24/2023 BRIAN SULLIVAN
Permit Finaled 10/2/2023 DEROLD HAUFF
CofO Issued 10/2/2023 DEROLD HAUFF
Permit Finaled 10/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/2/2020 RENZ SORIANO
Sewer availability Cleared 9/2/2020 RENZ SORIANO
Grading Pre-Inspection Cleared 10/7/2020 CARLOS MONTES
Specific Plan Cleared 1/15/2021 RUBEN VASQUEZ
ZI Cleared 1/15/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 1/21/2021 RENZ SORIANO

Contact Information

Contractor Resto Group The; Lic. No.: 898290-B 311 N ROBERTSON SUITE 732      BEVERLY HILLS, CA 90211
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 12/13/2021 Partial Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 1/5/2022 Conditional Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 3/1/2022 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 3/8/2022 Conditional Approval BRIAN SULLIVAN
Deputy Reinf. Concrete 6/21/2022 Conditional Approval BRIAN SULLIVAN
Deputy Steel/Welding 7/12/2022 Approved STUART CHAPMAN
Deputy Wood Construction 7/15/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 7/15/2022 Approved STUART CHAPMAN
HVAC-Rough 7/15/2022 Approved STUART CHAPMAN
PLUMBING-Rough 7/15/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/26/2022 Corrections Issued BRIAN SULLIVAN
Green Building Rough 7/26/2022 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/22/2022 Not Ready for Inspection BRIAN SULLIVAN
Shower Pan 8/26/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/31/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 9/13/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/13/2022 Partial Approval BRIAN SULLIVAN
Drywall Nailing 10/4/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/4/2022 Approved BRIAN SULLIVAN
Pre-Inspection 6/6/2023 Partial Inspection BRIAN SULLIVAN
Final 8/23/2023 OK to Issue CofO BRIAN SULLIVAN
Footing/Foundation/Slab 8/23/2023 Approved BRIAN SULLIVAN
Green Building Final 8/23/2023 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 8/23/2023 Approved BRIAN SULLIVAN