9811 S HOBART BLVD 90047
Certificate Information: 9811 S HOBART BLVD 90047
- Application / Permit
- 20014-10000-02393
- Plan Check / Job No.
- B20LA10083
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO S.F.D TO CREATE 2 NEW BATHROOMS AND A WALK IN CLOSET
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 5/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | RACHEL BEYENE |
| Corrections Issued | 7/8/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 7/16/2020 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 10/7/2020 | SHANGQIN XIE |
| Applicant returned to address corrections | 10/26/2020 | STARR CHEN |
| Plan Check Approved | 1/11/2021 | SINA KHOSRAVI |
| Issued | 1/19/2021 | APPLICANT |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| CofO in Progress | 4/26/2022 | FREDDIE RIVERA |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
| CofO Issued | 5/7/2022 | DEROLD HAUFF |
| Permit Finaled | 5/7/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 9/25/2020 | JUAN ASHTON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ogunbiyi,, Gbolahan Olayiwola; Lic. No.: C35221 | 20702 EL TORO ROAD STE 240 LAKE FOREST, CA 92630 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2021 | Approved | FREDDIE RIVERA |
| METHANE-Barrier | 10/19/2021 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 10/19/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 11/22/2021 | Approved | SABAS ALONSO |
| Insulation | 11/23/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/1/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 12/6/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/6/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 12/6/2021 | Approved | FREDDIE RIVERA |
| Insulation | 12/13/2021 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 12/15/2021 | Approved | FREDDIE RIVERA |
| Insulation | 12/16/2021 | No Access for Inspection | FREDDIE RIVERA |
| Drywall Nailing | 12/21/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 12/21/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 1/3/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 1/12/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | FREDDIE RIVERA |
| Final | 2/10/2022 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 2/10/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/10/2022 | Approved | FREDDIE RIVERA |
| METHANE-Final | 2/10/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 2/10/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 2/10/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 2/10/2022 | Approved | FREDDIE RIVERA |
| Final | 3/11/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 3/17/2022 | Corrections Issued | FREDDIE RIVERA |