9031 W ALTO CEDRO DR 90210

Certificate Information: 9031 W ALTO CEDRO DR 90210

Application / Permit
20014-10000-02339
Plan Check / Job No.
B20LA09851
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
RENOVATION OF GROUND FLOOR & ADDITION ON SECOND FLOOR
Permit Issued
Issued on 11/6/2020
Issuing Office
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 DANIEL YIP
Corrections Issued 6/26/2020 DANIEL YIP
Quality Review Completed 7/6/2020 QUAN NGHIEM
Building Plans Picked Up 7/8/2020 APPLICANT
Applicant returned to address corrections 10/19/2020 DANIEL YIP
Plan Check Approved 11/4/2020 DANIEL YIP
Issued 11/6/2020 APPLICANT
CofO in Progress 8/14/2025 RAUL BARAJAS
No Progress 8/16/2025 DEROLD HAUFF
CofO in Progress 8/16/2025 DEROLD HAUFF
No Progress 11/10/2025 DEROLD HAUFF
CofO in Progress 11/10/2025 DEROLD HAUFF
Permit Finaled 1/30/2026 DEROLD HAUFF
CofO Issued 1/30/2026 DEROLD HAUFF
Permit Finaled 1/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2020 CATHERINE ADROVER
Sewer availability Cleared 7/22/2020 CATHERINE ADROVER
Low Impact Development Cleared 9/29/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/2/2020 DINAH GARIN
Specific Plan Cleared 10/2/2020 LIZZI BEDUYA
ZI Cleared 10/28/2020 JOE LUCKEY
GPI Written Notices Cleared 11/2/2020 DANIEL YIP
Grading Pre-Inspection Cleared 11/2/2020 DANIEL YIP
Green Code Cleared 11/2/2020 DANIEL YIP

Contact Information

Contractor Usa General Contractors Inc; Lic. No.: 1044168-B 23036 BRYCE STREET      WOODLAND HILLS, CA 91364
Engineer Amoroso,, Gregory Michael; Lic. No.: L8771 24269 PALO VERDE DR      VALENCIA, CA 91354
Engineer Herrera,, Edgar E; Lic. No.: C67603 1971 S SUNRISE DRIVE      MONTEREY PARK, CA 91754

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2020 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 11/13/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 11/17/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval RAUL BARAJAS
Deputy Wood Construction 3/26/2021 No Access for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Conditional Approval RAUL BARAJAS
PLUMBING-Rough 4/5/2021 Approved RAUL BARAJAS
Wood Frame 4/5/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 4/14/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 4/14/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 4/14/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 4/23/2021 Partial Approval RAUL BARAJAS
Gas Test 4/23/2021 Corrections Issued RAUL BARAJAS
BUILDING-Rough-Frame 9/2/2021 Approved RAUL BARAJAS
Green Building Rough 9/2/2021 Approved RAUL BARAJAS
Insulation 11/8/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/8/2021 Approved RAUL BARAJAS
Drywall Nailing 12/2/2021 Approved RAUL BARAJAS
Shower Pan 3/14/2022 Approved RAUL BARAJAS
Pre-Gunite 4/14/2022 Not Ready for Inspection RAUL BARAJAS
Special/Order Compliance 10/6/2022 Partial Inspection RAUL BARAJAS
Final 12/5/2023 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 12/5/2023 Approved RAUL BARAJAS
Green Building Final 12/5/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/5/2023 SGSOV Approved RAUL BARAJAS
Smoke Detectors 12/5/2023 Approved RAUL BARAJAS
Final 1/4/2024 Corrections Issued RAUL BARAJAS
Final 4/16/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 4/18/2024 Not Ready for Inspection RAUL BARAJAS
Final 4/18/2024 Not Ready for Inspection RAUL BARAJAS
Gas Test 4/18/2024 Approved RAUL BARAJAS
HVAC-Final 4/18/2024 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Final 4/18/2024 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 5/10/2024 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 5/16/2024 Approved RAUL BARAJAS
Final 5/22/2024 Corrections Issued RAUL BARAJAS
Final 8/13/2025 OK to Issue CofO RAUL BARAJAS
Special/Order Compliance 11/7/2025 Corrections Issued SCOTT FINNILA