704 W 103RD ST 90044
Certificate Information: 704 W 103RD ST 90044
- Application / Permit
- 20014-10000-02332
- Plan Check / Job No.
- B20LA09835
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION 289 SF 1 BDRM, 1BA, 1 CLOSET
- Permit Issued
- Issued on 5/19/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2020 | ADAM HEGAZI |
| Corrections Issued | 6/8/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 3/28/2021 | ZAW HAN |
| Plan Check Approved | 3/31/2021 | ZAW HAN |
| Building Plans Picked Up | 4/1/2021 | APPLICANT |
| Issued | 5/19/2021 | APPLICANT |
| CofO in Progress | 9/21/2023 | JAMES CHAVEZ |
| Permit Finaled | 9/21/2023 | ANSON MAGLASANG |
| CofO Issued | 9/21/2023 | ANSON MAGLASANG |
| Permit Finaled | 9/21/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2021 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 3/9/2021 | ROSA SILVA |
Contact Information
| Contractor | Alberto Pacheco Construction Co.; Lic. No.: 1049644-B | 142 N AZUSA AVE AZUSA, CA 91702 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 6/23/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 7/7/2021 | Partial Approval | EUGENE CASSIDY |
| Green Building Final | 7/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 7/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Piling/Pier/Caisson | 7/7/2021 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 7/7/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2021 | Approved | EUGENE CASSIDY |
| Wood Frame | 7/26/2021 | Approved | EUGENE CASSIDY |
| Insulation | 7/28/2021 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 8/3/2021 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/3/2021 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 8/3/2021 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/1/2021 | Approved | EUGENE CASSIDY |
| Final | 9/1/2021 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 9/1/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/8/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 8/8/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Smoke Detectors | 8/8/2023 | Approved | JAMES CHAVEZ |
| Final | 8/17/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 8/17/2023 | Approved | JAMES CHAVEZ |