6257 E TIPTON WAY 90042

Certificate Information: 6257 E TIPTON WAY 90042

Application / Permit
20014-10000-02329
Plan Check / Job No.
B20LA09819
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
BEDROOM AND PATIO ADDITION TO (E) SINGLE FAMILY DWELLING WITH BATHROOM AND LAUNDRY REMODEL
Permit Issued
Issued on 3/24/2021
Issuing Office
Valley
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2020 APPLICANT
Assigned to Plan Check Engineer 6/9/2020 RAHEL BEYENE
Corrections Issued 6/17/2020 RAHEL BEYENE
Building Plans Picked Up 6/23/2020 APPLICANT
Applicant returned to address corrections 10/22/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 11/6/2020 FARSHAD ALIMOHAMADI
Issued 3/24/2021 APPLICANT
CofO in Progress 2/11/2022 CRAIG VAUGHAN
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/14/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 7/28/2020 WALLIE JONG
Sewer availability Cleared 7/28/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/31/2020 WALLIE JONG

Contact Information

Architect Ragle,, Benjamin David; Lic. No.: C32039 1608 MORTON AVENUE      LOS ANGELES, CA 90026
Contractor Hodara Raul Mauricio; Lic. No.: 861726-B 10220 DESOTO AVE #16      CHATSWORTH, CA 91311
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/21/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/6/2021 Partial Approval COREY HUPP
ELECTRICAL-Rough 7/6/2021 Approved COREY HUPP
Green Building Rough 7/6/2021 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 7/6/2021 Approved COREY HUPP
BUILDING-Rough-Frame 8/6/2021 Approved CRAIG VAUGHAN
Green Building Rough 8/6/2021 Approved CRAIG VAUGHAN
Insulation 8/24/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 8/24/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 9/7/2021 Approved CRAIG VAUGHAN
Final 2/4/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/4/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/4/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/8/2022 Approved CRAIG VAUGHAN
Final 2/8/2022 Conditional Approval CRAIG VAUGHAN
HVAC-Final 2/8/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 2/8/2022 Approved CRAIG VAUGHAN