830-830 1/2 E 84TH PL 90001
Certificate Information: 830-830 1/2 E 84TH PL 90001
- Application / Permit
- 20014-10000-02326
- Plan Check / Job No.
- B20LA09813
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT REAR PORTION OF (E) SFD INTO ATTACHED ADU PER STATE LAW, CREATING A SINGLE FAMILY DWELLING (1,090 SF) WITH ATTACHED ADU (600 SF)
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2020 | JESSE JIMENEZ |
| Corrections Issued | 6/10/2020 | JESSE JIMENEZ |
| Plan Check Approved | 9/10/2020 | RICARDO RAMIREZ |
| Issued | 9/22/2020 | APPLICANT |
| Building Plans Picked Up | 9/23/2020 | APPLICANT |
| CofO in Progress | 10/20/2022 | LILIANA PORTILLO |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 9/3/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 9/3/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 9/3/2020 | RENZ SORIANO |
Contact Information
| Contractor | Solis Carlos; Lic. No.: 732102-B | 1147 E 91ST ST LOS ANGELES, CA 90002 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 11/14/2020 | Corrections Issued | JOHN KLARIN |
| Insulation | 11/14/2020 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 11/14/2020 | Corrections Issued | JOHN KLARIN |
| Wood Frame | 11/14/2020 | Corrections Issued | JOHN KLARIN |
| Gas Test | 11/20/2020 | Partial Approval | DAVID FEILER |
| Insulation | 11/20/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 11/20/2020 | Corrections Issued | DAVID FEILER |
| Gas Test | 12/1/2020 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 12/1/2020 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 12/1/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 12/4/2020 | Approved | EUGENE CASSIDY |
| Insulation | 12/4/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 12/4/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 12/9/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 11/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/22/2021 | Corrections Issued | HORACE FULTZ |
| Gas Test | 11/22/2021 | Approved | HORACE FULTZ |
| HVAC-Final | 11/22/2021 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Final | 11/22/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 7/22/2022 | SGSOV Not Ready | ENRIQUE MIRELES |
| ELECTRICAL-Final | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Smoke Detectors | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/7/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/7/2022 | Approved | LILIANA PORTILLO |
| Final | 10/7/2022 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 10/7/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/7/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/7/2022 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 10/7/2022 | Approved | LILIANA PORTILLO |
| Final | 10/20/2022 | OK to Issue CofO | LILIANA PORTILLO |