3716 N LOADSTONE DR 91403

Certificate Information: 3716 N LOADSTONE DR 91403

Application / Permit
20014-10000-02303
Plan Check / Job No.
B20LA09750
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION OF 430 SF TO REAR OF (E) 1- STORY SFD AND 1-STORY ADDITION OF 69 SF TO (E) FRONT ATTACHED GARAGE. MAJOR REMODELING OF SFD AND ATTACHED GARAGE. REPLACE ROOF. DEMO 50 SF SFD.
Permit Issued
Issued on 1/19/2021
Issuing Office
Current Status
CofO Issued on 7/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 CHUNG-WEN CHUANG
Corrections Issued 7/7/2020 CHUNG-WEN CHUANG
Quality Review Completed 7/15/2020 KESETE HAREGOT
Building Plans Picked Up 7/27/2020 APPLICANT
Applicant returned to address corrections 10/15/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/22/2020 CHUNG-WEN CHUANG
Plan Check Approved 12/28/2020 CHUNG-WEN CHUANG
Issued 1/19/2021 APPLICANT
CofO in Progress 7/1/2022 JACK KARGODORIAN
Permit Finaled 7/13/2022 MICHAEL SMITH
CofO Issued 7/13/2022 MICHAEL SMITH
Permit Finaled 7/13/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/22/2020 ADRIAN CASTRO
Sewer availability Cleared 9/22/2020 ADRIAN CASTRO
Specific Plan Cleared 11/6/2020 LIZZI BEDUYA
ZI Cleared 11/6/2020 LIZZI BEDUYA
Low Impact Development Cleared 12/3/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/14/2020 ADRIAN CASTRO

Contact Information

Contractor Westland Contracting Inc; Lic. No.: 898301-B 2634 NORTH BEVERLY GLEN BLVD      LOS ANGELES, CA 90077
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/24/2021 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/26/2021 Approved CHARLES POWELL
Sewer 5/26/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 7/14/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 7/14/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/14/2021 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 7/14/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/20/2022 Corrections Issued JACK KARGODORIAN
HVAC-Rough 1/20/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 1/31/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 1/31/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 2/11/2022 Approved JACK KARGODORIAN
Wood Frame 2/11/2022 Approved JACK KARGODORIAN
Insulation 2/17/2022 Approved JACK KARGODORIAN
Drywall Nailing 3/4/2022 Partial Approval ASHLEY THOMPSON
Drywall Nailing 3/9/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 3/9/2022 Approved ASHLEY THOMPSON
Service/Power Release 5/10/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/22/2022 Approved JACK KARGODORIAN
Final 6/22/2022 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 6/22/2022 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 6/22/2022 Approved JACK KARGODORIAN
Final 7/1/2022 OK to Issue CofO JACK KARGODORIAN