14315 W COLLINS ST 91401
Certificate Information: 14315 W COLLINS ST 91401
- Application / Permit
- 20014-10000-02293
- Plan Check / Job No.
- B20LA09710
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO ADU AND ADDITION TO PROPOSED ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/16/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | CRYSTEL MAALOUF |
| Plan Check Approved | 8/19/2020 | CRYSTEL MAALOUF |
| Building Plans Picked Up | 8/20/2020 | APPLICANT |
| Issued | 9/16/2022 | APPLICANT |
| CofO in Progress | 8/7/2023 | RYAN SALAZAR |
| CofO Issued | 9/11/2023 | RUBEN SALAS |
| Permit Finaled | 9/11/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 7/24/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/24/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Byon,, Jin Sop; Lic. No.: C45122 | 2504 SIERRA LEONE AVE ROWLAND HEIGHTS, CA 91748 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2022 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 11/30/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 1/20/2023 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 1/20/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/25/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | MICHAEL SMITH |
| BUILDING-Rough-Frame | 2/10/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 2/10/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/23/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/3/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 3/3/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/10/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/15/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/17/2023 | Approved | RYAN SALAZAR |
| Insulation | 3/29/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 4/3/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/6/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/28/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/29/2023 | Approved | RYAN SALAZAR |
| Final | 6/29/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/29/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 6/29/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 6/29/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 6/29/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 7/3/2023 | Approved | RYAN SALAZAR |
| Final | 8/7/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 8/7/2023 | Approved | RYAN SALAZAR |