5140 S 6TH AVE 90043
Certificate Information: 5140 S 6TH AVE 90043
- Application / Permit
- 20014-10000-02291
- Plan Check / Job No.
- B20LA09702
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW TWO-STORY DETACHED ACCESSORY DWELLING UNIT (1200 SF MAX PER ORDINANCE, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 11/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2020 | AUNG SOE |
| Corrections Issued | 6/23/2020 | AUNG SOE |
| Quality Review Completed | 7/1/2020 | QUAN NGHIEM |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Applicant returned to address corrections | 2/9/2021 | AUNG SOE |
| Applicant returned to address corrections | 3/17/2021 | AUNG SOE |
| Applicant returned to address corrections | 10/5/2021 | AUNG SOE |
| Plan Check Approved | 10/6/2021 | AUNG SOE |
| Issued | 11/18/2021 | APPLICANT |
| CofO in Progress | 4/19/2023 | ANTHONY EGSON |
| CofO Issued | 4/20/2023 | DEROLD HAUFF |
| Permit Finaled | 4/20/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2020 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 12/10/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/28/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 1/5/2021 | KURT CORRAL |
| Green Code | Cleared | 3/22/2021 | AUNG SOE |
| Low Impact Development | Cleared | 9/7/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 12/20/2021 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/28/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 12/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 1/27/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/27/2022 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 1/27/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/17/2022 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 2/17/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 2/17/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/12/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/17/2022 | Approved | ANTHONY EGSON |
| Sewer | 8/17/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 9/30/2022 | Approved | ANTHONY EGSON |
| Insulation | 9/30/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 10/27/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/10/2023 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 2/10/2023 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 2/10/2023 | Not Ready for Inspection | RUBEN SALAS |
| BUILDING-Rough-Frame | 2/17/2023 | Approved | STUART CHAPMAN |
| Final | 2/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/17/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 2/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/17/2023 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/17/2023 | Approved | STUART CHAPMAN |
| Final | 2/28/2023 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 2/28/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 2/28/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 4/19/2023 | OK to Issue CofO | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 4/19/2023 | Approved | ANTHONY EGSON |