- ACCESSORY DWELLING UNIT IN A DETTACHED GARAGE (18' X 20') AND TO ADD 205.3 SF IN ADU. "COMPLY WITH THE DEPARTMENT ORDER EFFECTIVE DATE 03/12/20. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. "
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | ADAM HEGAZI |
| Corrections Issued | 6/3/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 10/21/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 10/26/2020 | APPLICANT |
| Plan Check Approved | 11/18/2020 | JESSE JIMENEZ |
| Issued | 12/1/2020 | APPLICANT |
| CofO in Progress | 8/26/2022 | THOMAS WOODS |
| CofO Issued | 8/30/2022 | DAVID JAMES |
| Permit Finaled | 8/30/2022 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Construction within easement | Cleared | 9/13/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Builder 20; Lic. No.: 1023066-B | 1817 N AVENUE 56 LOS ANGELES, CA 90042 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/14/2021 | Partial Approval | THOMAS WOODS |
| Pre-Inspection | 1/14/2021 | Not Ready for Inspection | THOMAS WOODS |
| Excavation/Setback/Form/Re-Bar | 1/26/2021 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 1/26/2021 | Not Ready for Inspection | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 2/3/2021 | Partial Approval | MICKEY YAMASHITA |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Approved | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 2/3/2021 | Corrections Issued | MICKEY YAMASHITA |
| Underground Mechanical | 2/3/2021 | Partial Inspection | MICKEY YAMASHITA |
| Sewer | 2/8/2021 | Approved | MICKEY YAMASHITA |
| Underground Mechanical | 2/8/2021 | Partial Approval | MICKEY YAMASHITA |
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Approved | THOMAS WOODS |
| Underground Mechanical | 2/12/2021 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 5/11/2021 | Approved | THOMAS WOODS |
| Deputy Drilled-In Anchors | 5/11/2021 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 5/11/2021 | Approved | THOMAS WOODS |
| Gas Test | 5/11/2021 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 5/11/2021 | Corrections Issued | THOMAS WOODS |
| PLUMBING-Rough | 5/12/2021 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 6/17/2021 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 6/17/2021 | Approved | THOMAS WOODS |
| Gas Test | 6/17/2021 | Approved | THOMAS WOODS |
| Green Building Rough | 6/17/2021 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 6/17/2021 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 6/17/2021 | Corrections Issued | THOMAS WOODS |
| PLUMBING-Rough | 7/6/2021 | Approved | THOMAS WOODS |
| Insulation | 9/14/2021 | Approved | THOMAS WOODS |
| Drywall Nailing | 9/17/2021 | Conditional Approval | MICKEY YAMASHITA |
| HVAC-Rough | 9/17/2021 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Final | 1/14/2022 | Corrections Issued | THOMAS WOODS |
| HVAC-Final | 1/14/2022 | Corrections Issued | THOMAS WOODS |
| HVAC-Rough | 1/14/2022 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 3/11/2022 | No Access for Inspection | THOMAS WOODS |
| Final | 6/24/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 6/24/2022 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 6/24/2022 | Corrections Issued | MICKEY YAMASHITA |
| Final | 7/5/2022 | No Access for Inspection | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | MICKEY YAMASHITA |
| Smoke Detectors | 7/5/2022 | No Access for Inspection | MICKEY YAMASHITA |
| ELECTRICAL-Final | 7/25/2022 | Approved | THOMAS WOODS |
| Final | 7/25/2022 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 7/25/2022 | Approved | THOMAS WOODS |
| HVAC-Final | 7/25/2022 | Approved | THOMAS WOODS |
| PLUMBING-Final | 7/25/2022 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 7/25/2022 | Approved | THOMAS WOODS |
| Final | 7/29/2022 | Corrections Issued | KIM BEAUCHAMP |
| Final | 8/4/2022 | No Access for Inspection | THOMAS WOODS |
| Final | 8/16/2022 | No Access for Inspection | THOMAS WOODS |
| Final | 8/17/2022 | Conditional Approval | THOMAS WOODS |
| Final | 8/26/2022 | OK to Issue CofO | THOMAS WOODS |