921 E 54TH ST 90011
Certificate Information: 921 E 54TH ST 90011
- Application / Permit
- 20014-10000-02242
- Plan Check / Job No.
- B20LA09536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 402 SF MSTR BDRM ADDITION, EXTEND THE LIVING ROOM 72SF INTO THE EXISTING FRONT PORCH AND REMODEL 72 SF OF THE EXISTING REAR PATIO AND DEMOLISH THE REST
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2020 | LUKE GONZALES |
| Corrections Issued | 6/3/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 8/4/2020 | PRANITA SHAH |
| Plan Check Approved | 11/7/2020 | PRANITA SHAH |
| Issued | 11/9/2020 | APPLICANT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| CofO in Progress | 8/22/2022 | JOAQUIN GREENOUGH |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
| CofO Issued | 9/11/2022 | DEROLD HAUFF |
| Permit Finaled | 9/11/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 7/9/2020 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | WALLIE JONG |
| Sewer availability | Cleared | 7/21/2020 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/11/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2021 | Partial Approval | ROBERT MCDOWELL |
| Green Building Rough | 3/15/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/15/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/28/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/28/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2021 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 4/28/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2021 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 6/18/2021 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 7/9/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Drywall Nailing | 7/23/2021 | Not Ready for Inspection | JESUS PINEDA |
| Insulation | 7/23/2021 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 7/23/2021 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 7/26/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 7/26/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/27/2021 | Approved | FREDDIE RIVERA |
| Final | 1/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Final | 1/28/2022 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 1/28/2022 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 1/28/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/18/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Not Ready | JUSTIN CURTIS |
| Smoke Detectors | 2/18/2022 | Not Ready for Inspection | JUSTIN CURTIS |
| Final | 2/25/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 2/25/2022 | Approved | STUART CHAPMAN |
| Final | 3/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 3/31/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Sewer | 3/31/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Final | 5/6/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| Sewer | 5/6/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 8/19/2022 | OK to Issue CofO | JOAQUIN GREENOUGH |