1370 W 26TH PL 90732

Certificate Information: 1370 W 26TH PL 90732

Application / Permit
20014-10000-02181
Plan Check / Job No.
B20LA09304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY BEDROOM AND FULL BATHROOM ADDITION TO THE REAR OF THE EXISTING SFD AND REMODEL (E) 3/4 BATHROOM.
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 8/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 CRISTINA SALAZAR
Corrections Issued 5/28/2020 CRISTINA SALAZAR
Plan Check Approved 12/28/2020 FERNANDO FLORES
Building Plans Picked Up 12/30/2020 APPLICANT
Issued 2/4/2021 APPLICANT
CofO in Progress 8/3/2022 ANSON MAGLASANG
Permit Finaled 8/4/2022 DEROLD HAUFF
Permit Finaled 8/4/2022 DEROLD HAUFF
CofO Issued 8/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/16/2020 YEGANEH SADEGHI
Roof/Waste drainage to street Cleared 12/16/2020 YEGANEH SADEGHI
Coastal Zone Cleared 12/21/2020 RICHARD REASER
Grading Pre-Inspection Cleared 12/26/2020 CRISTINA SALAZAR

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2021 Corrections Issued JOHN KLARIN
Deputy Drilled-In Anchors 6/15/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 6/15/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 7/1/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval JOHN KLARIN
Green Building Rough 7/1/2021 Partial Approval JOHN KLARIN
Insulation 7/1/2021 Partial Approval JOHN KLARIN
PLUMBING-Rough 7/1/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 7/29/2021 Partial Approval ANSON MAGLASANG
Green Building Rough 7/29/2021 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 8/16/2021 Approved JOHN KLARIN
PLUMBING-Rough 8/16/2021 Approved JOHN KLARIN
Drywall Nailing 8/26/2021 Approved ANSON MAGLASANG
Green Building Rough 8/26/2021 Approved ANSON MAGLASANG
Interior/Exterior Lathing 8/26/2021 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 12/30/2021 Partial Approval ANSON MAGLASANG
ELECTRICAL-Rough 12/30/2021 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 12/30/2021 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 6/8/2022 Approved ANSON MAGLASANG
Final 6/8/2022 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 6/8/2022 Approved ANSON MAGLASANG
Green Building Final 6/8/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 6/8/2022 Approved ANSON MAGLASANG
Final 8/2/2022 OK to Issue CofO ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved ANSON MAGLASANG
Service/Power Release 8/2/2022 Approved ANSON MAGLASANG