7318 N REMMET AVE 91303

Certificate Information: 7318 N REMMET AVE 91303

Application / Permit
20014-10000-02175
Plan Check / Job No.
B20LA09270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION AT REAR OF SFD PER WFPP.
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 11/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Assigned to Plan Check Engineer 5/26/2020 SINA KHOSRAVI
Corrections Issued 5/26/2020 SINA KHOSRAVI
Applicant returned to address corrections 6/9/2020 LUKE GONZALES
Applicant returned to address corrections 7/1/2020 CRISTINA SALAZAR
Plan Check Approved 7/14/2020 RICARDO RAMIREZ
Issued 7/28/2020 APPLICANT
Building Plans Picked Up 7/29/2020 APPLICANT
CofO in Progress 11/3/2020 HENRY KIM
CofO Issued 11/9/2020 JOHN JANSON
Permit Finaled 11/9/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/4/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 6/4/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/4/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2020 Corrections Issued HENRY KIM
Pre-Inspection 8/17/2020 Approved HENRY KIM
Footing/Foundation/Slab 8/18/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/24/2020 Partial Approval HENRY KIM
Insulation 8/24/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 8/28/2020 Approved HENRY KIM
ELECTRICAL-Rough 8/28/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Approved HENRY KIM
Green Building Rough 8/28/2020 Approved HENRY KIM
Insulation 9/2/2020 Approved HENRY KIM
Interior/Exterior Lathing 9/2/2020 Approved HENRY KIM
Drywall Nailing 9/8/2020 Approved HENRY KIM
ELECTRICAL-Final 10/20/2020 Corrections Issued HENRY KIM
Final 10/20/2020 Corrections Issued HENRY KIM
Green Building Final 10/20/2020 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 10/20/2020 SGSOV Approved HENRY KIM
Smoke Detectors 10/20/2020 Approved HENRY KIM
ELECTRICAL-Final 11/2/2020 Approved HENRY KIM
Final 11/2/2020 OK to Issue CofO HENRY KIM
HVAC-Final 11/2/2020 Approved HENRY KIM
PLUMBING-Final 11/2/2020 Approved HENRY KIM