14312 W ROBLAR PL 91423
Certificate Information: 14312 W ROBLAR PL 91423
- Application / Permit
- 20014-10000-02172
- Plan Check / Job No.
- B20LA09250
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLR MAIN HOME ADDITION 119 SF CONSISTING OF ADDITION TO EXISTING MASTER BEDROOM. 7'X17' TO THE REAR
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 8/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2020 | LUKE GONZALES |
| Corrections Issued | 5/27/2020 | LUKE GONZALES |
| Plan Check Approved | 8/31/2020 | RICARDO RAMIREZ |
| Issued | 9/10/2020 | APPLICANT |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| CofO in Progress | 12/21/2020 | CHRISTOPHE COCHRAN |
| CofO in Progress | 12/21/2020 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/3/2022 | DANIEL ORRANTE |
| CofO Issued | 8/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/10/2020 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | J D R Construction; Lic. No.: 991165-B | 4813 W AVE J4 LANCASTER, CA 93536 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/13/2020 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 10/13/2020 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 10/21/2020 | Corrections Issued | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 10/21/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 10/27/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 10/27/2020 | Corrections Issued | CHARLES POWELL |
| Drywall Nailing | 10/29/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 10/29/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/29/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/15/2020 | Approved | CHARLES POWELL |
| Final | 12/15/2020 | OK to Issue CofO | CHARLES POWELL |
| Green Building Final | 12/15/2020 | Approved | CHARLES POWELL |
| Green Building Rough | 12/15/2020 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 12/15/2020 | SGSOV Approved | CHARLES POWELL |
| Smoke Detectors | 12/15/2020 | Approved | CHARLES POWELL |