2640-2642 N QUEEN ST 90039

Certificate Information: 2640-2642 N QUEEN ST 90039

Application / Permit
20014-10000-02169
Plan Check / Job No.
B20LA09229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2-STORY ADDITION AND CONVERT SFD UNIT INTO A DUPLEX. 990.0 SF (N) ADDITION INTERIOR REMODEL. ENCLOSURE CARPORT 75.0 SF
Permit Issued
Issued on 1/11/2022
Issuing Office
Current Status
CofO Issued on 12/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2020 APPLICANT
Building Plans Picked Up 5/27/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 SERGIO GUTIERREZ
Corrections Issued 6/18/2020 SERGIO GUTIERREZ
Quality Review Completed 6/23/2020 KESETE HAREGOT
Green Plans Picked Up 6/24/2020 APPLICANT
Plan Check Approved 10/13/2021 SERGIO GUTIERREZ
Issued 1/11/2022 APPLICANT
CofO in Progress 12/7/2023 THOMAS LOGRASSO
Permit Finaled 12/22/2023 DEROLD HAUFF
CofO Issued 12/22/2023 DEROLD HAUFF
Permit Finaled 12/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 11/24/2020 SARAHI ORTEGA
ZI Cleared 11/24/2020 SARAHI ORTEGA
Highway dedication Cleared 1/5/2021 CECILIO NAVARRO
Address approval Cleared 1/6/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 1/6/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 1/6/2021 MATTHEW CRAIG
Sewer availability Cleared 1/6/2021 CECILIO NAVARRO
Low Impact Development Cleared 7/30/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/7/2021 RENZ SORIANO
Green Code Cleared 10/13/2021 VIVIAN LAO

Contact Information

Contractor Usa General Contractors Inc; Lic. No.: 1044168-B 23036 BRYCE STREET      WOODLAND HILLS, CA 91364
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2022 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/8/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 2/8/2022 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/14/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 2/14/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 2/22/2022 Corrections Issued THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/6/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 4/6/2022 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 5/10/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 9/7/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 9/8/2022 Approved THOMAS LOGRASSO
HVAC-Rough 9/13/2022 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 9/13/2022 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 9/14/2022 Partial Approval THOMAS LOGRASSO
Wood Frame 9/19/2022 Corrections Issued RYAN SALAZAR
Deputy Wood Construction 9/20/2022 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 11/3/2022 Approved THOMAS LOGRASSO
Green Building Rough 11/3/2022 Approved THOMAS LOGRASSO
Insulation 11/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 11/3/2022 Partial Approval THOMAS LOGRASSO
MERV13>=Rough 11/3/2022 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 11/3/2022 Approved THOMAS LOGRASSO
Insulation 11/10/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 11/10/2022 Partial Approval THOMAS LOGRASSO
Insulation 11/15/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 11/16/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Rough 12/15/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 12/15/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 12/28/2022 Partial Approval THOMAS LOGRASSO
Drywall Nailing 12/29/2022 Partial Approval JOSE AVILA
ELECTRICAL-Rough 3/10/2023 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 3/16/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 3/16/2023 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 3/22/2023 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 3/28/2023 Approved THOMAS LOGRASSO
ELECTRICAL-Final 4/10/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 4/10/2023 Partial Inspection THOMAS LOGRASSO
Green Building Final 4/10/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 4/10/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 4/10/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 4/10/2023 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 4/10/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 8/15/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 8/15/2023 Approved THOMAS LOGRASSO
MERV13>=Final 8/15/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 8/15/2023 Approved THOMAS LOGRASSO
Final 9/7/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 9/7/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 9/28/2023 Not Ready for Inspection THOMAS LOGRASSO
MERV13>=Final 9/28/2023 Approved THOMAS LOGRASSO
PLUMBING-Final 9/28/2023 Approved THOMAS LOGRASSO
Final 12/7/2023 OK to Issue CofO THOMAS LOGRASSO