1852 N ROWAN AVE 90032
Certificate Information: 1852 N ROWAN AVE 90032
- Application / Permit
- 20014-10000-02155
- Plan Check / Job No.
- B20LA09196
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF EXISITNG STORAGE / GARAGE TO ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | STARR CHEN |
| Corrections Issued | 6/17/2020 | STARR CHEN |
| Quality Review Completed | 6/23/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 7/6/2020 | APPLICANT |
| Applicant returned to address corrections | 12/22/2020 | STARR CHEN |
| Plan Check Approved | 2/3/2021 | STARR CHEN |
| Issued | 3/10/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| CofO in Progress | 2/22/2022 | COREY HUPP |
| Permit Finaled | 8/23/2022 | DEROLD HAUFF |
| CofO Issued | 8/23/2022 | DEROLD HAUFF |
| Permit Finaled | 8/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | WALLIE JONG |
| Sewer availability | Cleared | 7/13/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2020 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 8/28/2020 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 12/1/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/1/2020 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 12/22/2020 | STARR CHEN |
| Green Code | Cleared | 12/22/2020 | STARR CHEN |
Contact Information
| Contractor | Professional Home Repair; Lic. No.: 1026152-B | P O BOX 43271 BAKERSFIELD, CA 93384 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 900 N SANTA ANITA AVE STE B ARCADIA, CA 91006 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/31/2021 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/14/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | OSVALDO PARAMO |
| Posting Pre-Inspection | 6/17/2021 | Partial Inspection | COREY HUPP |
| Deck | 6/24/2021 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Partial Approval | OSVALDO PARAMO |
| Sewer | 7/27/2021 | Approved | COREY HUPP |
| Underground Mechanical | 7/28/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 8/16/2021 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 8/16/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 8/16/2021 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 8/18/2021 | Approved | COREY HUPP |
| HVAC-Rough | 8/18/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 8/18/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 8/25/2021 | Approved | COREY HUPP |
| Green Building Rough | 8/25/2021 | Approved | COREY HUPP |
| HVAC-Rough | 8/25/2021 | Approved | COREY HUPP |
| Insulation | 8/30/2021 | Conditional Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 8/30/2021 | Partial Approval | SCOTT FINNILA |
| Insulation | 9/1/2021 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 9/3/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 10/22/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 11/16/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 11/16/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 11/16/2021 | Approved | COREY HUPP |
| Final | 1/12/2022 | No Access for Inspection | COREY HUPP |
| Green Building Final | 1/12/2022 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Not Ready | COREY HUPP |
| Final | 1/20/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 1/20/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | OSVALDO PARAMO |
| Final | 1/26/2022 | Corrections Issued | AMY COLIN |
| Gas Test | 1/27/2022 | Approved | LILIANA PORTILLO |
| Final | 2/8/2022 | Corrections Issued | COREY HUPP |
| Final | 2/11/2022 | Corrections Issued | COREY HUPP |
| Final | 2/22/2022 | OK to Issue CofO | COREY HUPP |