815 E INDIANA AVE 90291

Certificate Information: 815 E INDIANA AVE 90291

Application / Permit
20014-10000-02145
Plan Check / Job No.
B20LA09154
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE AND CONVERT (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33
Permit Issued
Issued on 2/1/2021
Issuing Office
Current Status
CofO Issued on 5/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 DANIEL YIP
Corrections Issued 6/18/2020 DANIEL YIP
Quality Review Completed 6/30/2020 QUAN NGHIEM
Green Plans Picked Up 7/8/2020 APPLICANT
Plan Check Approved 1/27/2021 DANIEL YIP
Issued 2/1/2021 APPLICANT
CofO in Progress 5/4/2023 EVAN COOPER
Permit Finaled 5/15/2023 DANIEL ORRANTE
CofO Issued 5/15/2023 DANIEL ORRANTE
Permit Finaled 5/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/27/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/29/2020 DINAH GARIN
Sewer availability Cleared 7/29/2020 DINAH GARIN
Low Impact Development Cleared 10/20/2020 ROBIN YAMADA
Coastal Zone Cleared 1/21/2021 DENZEL HENDERSON
Green Code Cleared 1/21/2021 DANIEL YIP
Roof/Waste drainage to street Cleared 1/25/2021 RAYMOND MUGAMBWA

Contact Information

Contractor S R L General Contractors Inc; Lic. No.: 761583-B 643 CYPRESS AVENUE      HERMOSA BEACH, CA 90254
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/5/2021 Approved JOHNNY MIRANDA
Pre-Inspection 2/11/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 3/17/2021 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 4/5/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/12/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/30/2021 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 5/10/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 6/17/2021 Conditional Approval JOHNNY MIRANDA
PLUMBING-Rough 6/17/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 7/1/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 7/21/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 7/21/2021 Approved BRENDAN LOONEY
Deputy Wood Construction 7/23/2021 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/26/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 7/26/2021 Approved JOHNNY MIRANDA
Green Building Rough 7/26/2021 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 8/3/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Insulation 8/9/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/9/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 8/17/2021 Approved JOHNNY MIRANDA
Drywall Nailing 8/17/2021 Approved JOHNNY MIRANDA
Green Building Rough 8/17/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/17/2021 Approved JOHNNY MIRANDA
Underground Mechanical 11/1/2021 Partial Approval DAVID FEILER
ELECTRICAL-Final 12/13/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Final 12/28/2021 Approved ENRIQUE MIRELES
Final 12/28/2021 Corrections Issued ENRIQUE MIRELES
HVAC-Final 12/28/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 12/28/2021 Approved ENRIQUE MIRELES
Gas Test 12/29/2021 No Access for Inspection DAVID FEILER
Final 4/5/2023 Corrections Issued HERBERT GIRON
Green Building Final 4/5/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 4/5/2023 Approved HERBERT GIRON
Final 5/3/2023 OK to Issue CofO EVAN COOPER
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved EVAN COOPER