8004 S GLIDER AVE 90045
Certificate Information: 8004 S GLIDER AVE 90045
- Application / Permit
- 20014-10000-02144
- Plan Check / Job No.
- B20LA09153
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF AN (E) TWO-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- Current Status
- CofO Issued on 11/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | CRISTINA SALAZAR |
| Corrections Issued | 5/22/2020 | CRISTINA SALAZAR |
| Building Plans Picked Up | 6/8/2020 | APPLICANT |
| Plan Check Approved | 1/29/2021 | LUKE GONZALES |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 11/3/2023 | BOBBY KEY |
| Permit Finaled | 11/8/2023 | DANIEL ORRANTE |
| CofO Issued | 11/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 6/10/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 6/10/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2020 | EMIL KYUPELYAN |
| Construction near power lines | Cleared | 8/17/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/17/2020 | RIDWAN HARDY |
| Specific Plan | Cleared | 1/13/2021 | RUBEN VASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/16/2021 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 3/19/2021 | Partial Approval | DAVID HEINE |
| Underground Mechanical | 3/19/2021 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 4/7/2021 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 4/23/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/23/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 5/24/2021 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 7/1/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/5/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 10/5/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/6/2021 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/3/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 1/3/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/3/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 5/31/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 5/31/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/25/2022 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 10/25/2022 | Approved | BOBBY KEY |
| Green Building Rough | 10/25/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 10/25/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | BOBBY KEY |
| Shower Pan | 10/25/2022 | Approved | BOBBY KEY |
| Insulation | 11/8/2022 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 11/18/2022 | Conditional Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 12/22/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 12/22/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 12/22/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 12/22/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/10/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 9/19/2023 | Approved | BOBBY KEY |
| Final | 9/19/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/19/2023 | Approved | BOBBY KEY |
| HVAC-Final | 9/19/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Final | 9/19/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/19/2023 | Approved | BOBBY KEY |
| Final | 11/3/2023 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 11/3/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 11/3/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | BOBBY KEY |
| Service/Power Release | 11/3/2023 | Approved | BOBBY KEY |