2721 W MOSS AVE 90065

Certificate Information: 2721 W MOSS AVE 90065

Application / Permit
20014-10000-02120
Plan Check / Job No.
B20LA09056
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING GARAGE CONVERSION TO ADU AND ADDITION "COMPLY WITH DEPARTMENT ORDER effective date 02/19/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 5/10/2022
Issuing Office
Current Status
Permit Finaled on 2/24/2026

Permit Application Status History

Submitted 7/4/2020 APPLICANT
Assigned to Plan Check Engineer 7/24/2020 MAHNAZ NOURHASHEMI
Corrections Issued 7/27/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 7/31/2020 TIEN JEN WANG
Building Plans Picked Up 11/17/2020 APPLICANT
Applicant returned to address corrections 1/6/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 5/4/2022 MAHNAZ NOURHASHEMI
Issued 5/10/2022 APPLICANT
Permit Finaled 2/23/2026 JACOB SEGURA

Permit Application Clearance Information

Address approval Cleared 1/25/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/16/2021 CECILIO NAVARRO
Sewer availability Cleared 6/18/2021 CECILIO NAVARRO
Low Impact Development Cleared 7/9/2021 MITESH PATEL
Grading Pre-Inspection Cleared 1/19/2022 VASIL MIHALEV
Roof/Waste drainage to street Cleared 1/19/2022 JEANIE LAM
Hydrant and Access approval Cleared 1/22/2022 RUEL COLE
GPI Written Notices Cleared 4/26/2022 MAHNAZ NOURHASHEMI

Contact Information

Architect Gutierrez,, Juan Antonio; Lic. No.: C33231 15622 PATRONELLA AVENUE      GARDENA, CA 90249
Contractor Owner-Builder       ,

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/1/2022 Approved JAVIER RAMOS SR
Pre-Inspection 12/9/2024 Corrections Issued JACOB SEGURA
Footing/Foundation/Slab 9/3/2025 Corrections Issued JACOB SEGURA
BUILDING-Rough-Frame 1/29/2026 Approved JACOB SEGURA
Drywall Nailing 1/29/2026 Approved JACOB SEGURA
ELECTRICAL-Final 1/29/2026 Approved JACOB SEGURA
ELECTRICAL-Rough 1/29/2026 Approved JACOB SEGURA
Final 1/29/2026 Corrections Issued JACOB SEGURA
Footing/Foundation/Slab 1/29/2026 Approved JACOB SEGURA
Green Building Final 1/29/2026 Approved JACOB SEGURA
Green Building Rough 1/29/2026 Approved JACOB SEGURA
Insulation 1/29/2026 Approved JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Not Ready JACOB SEGURA
Smoke Detectors 1/29/2026 Approved JACOB SEGURA
Final 2/23/2026 Permit Finaled JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved JACOB SEGURA