2561 W HYLER AVE 90041

Certificate Information: 2561 W HYLER AVE 90041

Application / Permit
20014-10000-02115
Plan Check / Job No.
B20LA09042
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION AND DECK ADDITION AT REAR TO EXISTING SFD. REMODEL KITCHEN, CONVERT EXISTING 3 BEDROOM/ 1 BATH TO 3 BEDROOM/ 2 BATH, NEW LAUNDRY.
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2020 APPLICANT
Assigned to Plan Check Engineer 5/22/2020 LUKE GONZALES
Corrections Issued 5/22/2020 LUKE GONZALES
Applicant returned to address corrections 8/31/2020 CRISTINA SALAZAR
Applicant returned to address corrections 10/7/2020 SAMUEL GONZALEZ
Building Plans Picked Up 10/13/2020 APPLICANT
Plan Check Approved 10/26/2020 SAMUEL GONZALEZ
Issued 11/10/2020 APPLICANT
CofO in Progress 11/13/2021 CHRIS CHRISTENSEN
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/14/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/16/2020 JEANIE LAM
Grading Pre-Inspection Cleared 10/26/2020 LUKE GONZALES

Contact Information

Contractor Iconx Inc; Lic. No.: 980801-B 4248 PANAMINT STREET      LOS ANGELES, CA 90065

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/8/2020 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 12/8/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 12/11/2020 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/31/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 3/31/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/31/2021 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 4/22/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/27/2021 Corrections Issued CRAIG VAUGHAN
Wood Frame 5/6/2021 Partial Approval CRAIG VAUGHAN
Insulation 5/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 5/28/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/28/2021 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 5/28/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/8/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/8/2021 Partial Approval HAMIK HARTOUNIAN
Insulation 6/8/2021 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/8/2021 Approved HAMIK HARTOUNIAN
Gas Test 10/7/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Ready BRIAN SULLIVAN
Final 11/8/2021 Corrections Issued CRAIG VAUGHAN
Final 11/12/2021 OK to Issue CofO CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/12/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/12/2021 Approved CHRIS CHRISTENSEN