3423 S 8TH AVE 90018

Certificate Information: 3423 S 8TH AVE 90018

Application / Permit
20014-10000-02073
Plan Check / Job No.
B20LA08911
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING SFD AT REAR TO 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d). "COMPLY WITH DEPARTMENT ORDER effective date 02/10/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 CRYSTEL MAALOUF
Corrections Issued 6/16/2020 CRYSTEL MAALOUF
Quality Review Completed 7/5/2020 TU HUA
Applicant returned to address corrections 2/18/2021 CRYSTEL MAALOUF
Plan Check Approved 2/24/2021 CRYSTEL MAALOUF
Issued 2/24/2021 APPLICANT
CofO in Progress 7/13/2021 JESSE CHEN
Permit Finaled 9/3/2021 BRUCE TODD
CofO Issued 9/3/2021 BRUCE TODD
Permit Finaled 9/3/2021 BRUCE TODD

Permit Application Clearance Information

Construction near power lines Cleared 12/14/2020 RIDWAN HARDY
Address approval Cleared 12/23/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/23/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 12/23/2020 RENZ SORIANO
Sewer availability Cleared 12/23/2020 RENZ SORIANO
Green Code Cleared 2/18/2021 CRYSTEL MAALOUF

Contact Information

Contractor Softwood Contractors Inc; Lic. No.: 1021044-B P O BOX 40315      DOWNEY, CA 90239
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/16/2021 Approved JESSE CHEN
Footing/Foundation/Slab 4/27/2021 Approved JESSE CHEN
ELECTRICAL-Rough 5/12/2021 Approved JESSE CHEN
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Approved JESSE CHEN
PLUMBING-Rough 5/12/2021 Approved JESSE CHEN
Wood Frame 5/17/2021 Approved JESSE CHEN
Insulation 5/24/2021 Approved JESSE CHEN
Drywall Nailing 6/1/2021 Approved JESSE CHEN
Interior/Exterior Lathing 6/1/2021 Partial Approval JESSE CHEN
BUILDING-Rough-Frame 7/13/2021 Approved JESSE CHEN
Final 7/13/2021 OK to Issue CofO JESSE CHEN
Green Building Final 7/13/2021 Approved JESSE CHEN
Green Building Rough 7/13/2021 Approved JESSE CHEN
Interior/Exterior Lathing 7/13/2021 Approved JESSE CHEN
SGSOV-Seismic Gas S/O Valve 7/13/2021 SGSOV Approved JESSE CHEN
Smoke Detectors 7/13/2021 Approved JESSE CHEN