425 E 43RD PL 90011
Certificate Information: 425 E 43RD PL 90011
- Application / Permit
- 20014-10000-02051
- Plan Check / Job No.
- B20LA08809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO THE EXIST ONE STORY SFD AS (N) 2-BEDROOMS & 1-BATHROOM 498 SF W/ NEW REAR PORCH 14SF
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 11/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2020 | TSE MING HUANG |
| Corrections Issued | 5/21/2020 | TSE MING HUANG |
| Plan Check Approved | 1/26/2021 | ADAM HEGAZI |
| Building Plans Picked Up | 1/27/2021 | APPLICANT |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 11/26/2025 | DANIEL ORRANTE |
| Permit Finaled | 11/26/2025 | DANIEL ORRANTE |
| CofO Issued | 11/26/2025 | DANIEL ORRANTE |
| Permit Finaled | 11/26/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/10/2020 | HELEN JADALI |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2020 | JEANIE LAM |
| Sewer availability | Cleared | 10/29/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 12/14/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/11/2021 | JEANIE LAM |
Contact Information
| Contractor | Tafoya'S Construction Inc; Lic. No.: 1041076-B | 877 DEL VALLE AVE LA PUENTE, CA 91744 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/20/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/26/2021 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/7/2021 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 9/7/2021 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/10/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 9/10/2021 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 9/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/29/2021 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/29/2021 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/2/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 12/2/2021 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 12/2/2021 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/2/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 12/13/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/16/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 12/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 12/21/2021 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/28/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 12/28/2021 | Partial Approval | ADAM ESCOTO |
| Shower Pan | 1/10/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 2/17/2022 | Approved | HORACE FULTZ |
| Final | 2/17/2022 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 2/17/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 2/17/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 2/17/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Approved | HORACE FULTZ |
| Service/Power Release | 2/17/2022 | Approved | HORACE FULTZ |
| Smoke Detectors | 2/17/2022 | Approved | HORACE FULTZ |
| Final | 11/25/2025 | Conditional Approval | DANIEL ORRANTE |