4751 N GLENALBYN DR 90065
Certificate Information: 4751 N GLENALBYN DR 90065
- Application / Permit
- 20014-10000-02030
- Plan Check / Job No.
- B20LA08680
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISTING 1-STORY SFD BE REMODELED AND ADDITION
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 9/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2020 | JESSE ARELLANO |
| Corrections Issued | 6/16/2020 | JESSE ARELLANO |
| Quality Review Completed | 6/26/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| Green Plans Picked Up | 8/26/2020 | APPLICANT |
| Applicant returned to address corrections | 9/26/2020 | JESSE ARELLANO |
| Plan Check Approved | 10/1/2020 | JESSE ARELLANO |
| Issued | 12/22/2020 | APPLICANT |
| CofO in Progress | 8/24/2021 | OSVALDO PARAMO |
| CofO in Progress | 8/24/2021 | OSVALDO PARAMO |
| Permit Finaled | 9/1/2021 | DEROLD HAUFF |
| CofO Issued | 9/1/2021 | DEROLD HAUFF |
| Permit Finaled | 9/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/19/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 8/19/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2020 | RENZ SORIANO |
| Green Code | Cleared | 8/25/2020 | JESSE ARELLANO |
| Hydrant and Access approval | Cleared | 9/10/2020 | MATTHEW CRAIG |
| Specific Plan | Cleared | 9/10/2020 | NASHYA JENSEN |
Contact Information
| Contractor | Dellergo Development & Construction; Lic. No.: 882785-B | 244 REDONDO AVENUE LONG BEACH, CA 90803 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/12/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 3/22/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/30/2021 | Approved | OSVALDO PARAMO |
| Wood Frame | 4/8/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 4/19/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/19/2021 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 4/19/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 4/29/2021 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/22/2021 | Approved | OSVALDO PARAMO |
| Final | 6/22/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/22/2021 | Approved | OSVALDO PARAMO |
| Green Building Rough | 6/22/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 6/22/2021 | Approved | OSVALDO PARAMO |
| Final | 7/16/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | OSVALDO PARAMO |
| Final | 7/20/2021 | Conditional Approval | OSVALDO PARAMO |
| Gas Test | 7/20/2021 | Approved | OSVALDO PARAMO |
| Final | 7/21/2021 | Conditional Approval | OSVALDO PARAMO |
| Final | 7/30/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/9/2021 | Conditional Approval | OSVALDO PARAMO |
| Final | 8/11/2021 | Corrections Issued | OSVALDO PARAMO |
| Final | 8/24/2021 | OK to Issue CofO | OSVALDO PARAMO |