1233 N AVENUE 56 90042
Certificate Information: 1233 N AVENUE 56 90042
- Application / Permit
- 20014-10000-02014
- Plan Check / Job No.
- B20LA08595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AN EXISTING 14' x 16' DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT (ADU) AND ADD 130 SF ADU EXTENSION
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2020 | CARLOS MONTES |
| Corrections Issued | 5/28/2020 | CARLOS MONTES |
| Quality Review Completed | 5/28/2020 | JASON HEALEY |
| Building Plans Picked Up | 5/29/2020 | APPLICANT |
| Applicant returned to address corrections | 8/14/2020 | CARLOS MONTES |
| Green Plans Picked Up | 9/23/2020 | APPLICANT |
| Applicant returned to address corrections | 2/26/2021 | CARLOS MONTES |
| Plan Check Approved | 11/9/2021 | CARLOS MONTES |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 2/21/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
| CofO Issued | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 2/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2020 | THOMAS LANG |
| Green Code | Cleared | 9/22/2020 | CARLOS MONTES |
| Sewer availability | Cleared | 11/5/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 2/4/2021 | JORGE MEJIA LEMUS |
| Grading Pre-Inspection | Cleared | 2/17/2021 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | WALLIE JONG |
Contact Information
| Architect | Hill,, Samantha Joyce; Lic. No.: C35348 | 1441 HUNTINGTON DRIVE #192 SOUTH PASADENA, CA 91030 |
| Contractor | Kipsen Company Corporation; Lic. No.: 1035781-B | 2292 FARADAY AVE SUITE 100 CARLSBAD, CA 92008 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 1/18/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/18/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/21/2023 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/21/2023 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/5/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 7/24/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/20/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 11/20/2023 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/12/2023 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 12/12/2023 | Partial Approval | ROY SPAULDING |
| HVAC-Rough | 12/12/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 12/12/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/19/2023 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 12/19/2023 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 12/21/2023 | Approved | ROY SPAULDING |
| Insulation | 12/28/2023 | Corrections Issued | BRENDAN MORELLI |
| Insulation | 1/11/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 1/11/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 2/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 2/2/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/23/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/23/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 8/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 8/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/15/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 9/9/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 9/9/2024 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/8/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/5/2025 | Corrections Issued | CRAIG DAVIS |
| Final | 2/20/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |