9332 W NIGHTINGALE DR 90069
Certificate Information: 9332 W NIGHTINGALE DR 90069
- Application / Permit
- 20014-10000-02013
- Plan Check / Job No.
- B20LA08593
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1- STORY ADDITION TO (E) SFD
- Permit Issued
- Issued on 3/16/2021
- Issuing Office
- Current Status
- Issued on 3/16/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2020 | CARLOS MONTES |
| Corrections Issued | 6/3/2020 | CARLOS MONTES |
| Quality Review Completed | 6/8/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 6/22/2020 | APPLICANT |
| Applicant returned to address corrections | 2/4/2021 | CARLOS MONTES |
| Plan Check Approved | 3/8/2021 | CARLOS MONTES |
| Issued | 3/16/2021 | APPLICANT |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/17/2021 | BRIAN MILLER |
| Miscellaneous | Cleared | 2/18/2021 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2021 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | CELINA MORENO |
| Sewer availability | Cleared | 2/25/2021 | CELINA MORENO |
Contact Information
| Architect | Bondanelli,, Bruno; Lic. No.: C29801 | 24139 AFAMADO LANE DIAMOND BAR, CA 91765 |
| Contractor | Warwick Group; Lic. No.: 675774-B | 8800 VENICE BLVD SUITE 315 LOS ANGELES, CA 90034 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/13/2022 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 6/3/2022 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 6/14/2022 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/15/2022 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/15/2022 | Approved | RAUL BARAJAS |
| Deputy Steel/Welding | 7/27/2022 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 9/12/2022 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 2/22/2023 | Approved | RAUL BARAJAS |
| Sewer | 2/22/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/12/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 10/12/2023 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 10/12/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 11/30/2023 | Approved | RAUL BARAJAS |
| HVAC-Rough | 11/30/2023 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 11/30/2023 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/1/2023 | Conditional Approval | RAUL BARAJAS |
| Green Building Rough | 12/1/2023 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 12/1/2023 | Approved | RAUL BARAJAS |
| Insulation | 12/18/2023 | Corrections Issued | STUART CHAPMAN |
| Insulation | 12/22/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/12/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/12/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Shower Pan | 1/12/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/23/2024 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 2/20/2024 | Approved | ALIZAH MAYAGOITIA |
| Gas Test | 1/17/2025 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/3/2025 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Final | 9/5/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 9/5/2025 | Approved | DAVID WILLIAMS |
| Service/Power Release | 11/5/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 5/8/2026 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 5/8/2026 | Corrections Issued | BRENDAN MORELLI |