535 N CRANE BLVD 90065

Certificate Information: 535 N CRANE BLVD 90065

Application / Permit
20014-10000-02006
Plan Check / Job No.
B20LA08573
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY ADDITION TO THE SIDE OF (E) TWO-STORY SINGLE FAMILY DWELLING TO CONNECT (E) DETACHED GARAGE AND CONVERT (E) NON-HABITABLE LOWER LEVEL TO MASTER BEDROOM. SCOPE OF WORK TO INCLUDE ENCLOSING (E) COVERED PATIO, ADDITION OF STAIRS, BATHROOM, AND ROOFTOP WALKING DECK ABOVE LOWER LEVEL. ALL WORK PER ENGINEERING DESIGN.
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 MAHNAZ NOURHASHEMI
Corrections Issued 6/17/2020 MAHNAZ NOURHASHEMI
Quality Review Completed 7/1/2020 TIEN JEN WANG
Applicant returned to address corrections 10/21/2020 MAHNAZ NOURHASHEMI
Plan Check Approved 2/24/2021 MAHNAZ NOURHASHEMI
Issued 7/14/2021 APPLICANT
Building Plans Picked Up 1/31/2022 APPLICANT
CofO in Progress 3/6/2023 OSVALDO PARAMO
CofO in Progress 3/6/2023 OSVALDO PARAMO
Permit Finaled 4/6/2023 DEROLD HAUFF
CofO Issued 4/6/2023 DEROLD HAUFF
Permit Finaled 4/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Green Code Cleared 10/21/2020 MAHNAZ NOURHASHEMI
Specific Plan Cleared 12/31/2020 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 2/19/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 2/23/2021 ROSA SILVA

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Aragon,, Francisco J; Lic. No.: C69790 535 CRANE BLVD      LOS ANGELES, CA 90065

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/31/2021 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 9/8/2021 Partial Approval OSVALDO PARAMO
Pre-Inspection 10/27/2021 Approved OSVALDO PARAMO
Deputy Wood Construction 11/15/2021 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 12/6/2021 Approved OSVALDO PARAMO
ELECTRICAL-Rough 12/13/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 12/28/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 12/28/2021 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 12/28/2021 Not Ready for Inspection CRAIG VAUGHAN
Drywall Nailing 1/6/2022 Partial Approval AMY COLIN
Green Building Rough 1/6/2022 Partial Approval AMY COLIN
HVAC-Rough 1/6/2022 Approved AMY COLIN
Interior/Exterior Lathing 1/12/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 1/20/2022 Partial Approval OSVALDO PARAMO
Green Building Rough 1/20/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 1/20/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/31/2022 Approved OSVALDO PARAMO
Insulation 1/31/2022 Approved OSVALDO PARAMO
Drywall Nailing 2/10/2022 Approved OSVALDO PARAMO
Shower Pan 2/10/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/28/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 3/22/2022 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 3/22/2022 Not Ready for Inspection OSVALDO PARAMO
Final 7/27/2022 Partial Inspection OSVALDO PARAMO
Green Building Final 7/27/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 7/27/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 7/27/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 9/22/2022 Approved OSVALDO PARAMO
ELECTRICAL-Rough 10/6/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 10/6/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 10/12/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Approved OSVALDO PARAMO
HVAC-Rough 10/12/2022 Approved OSVALDO PARAMO
Insulation 10/18/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/18/2022 Approved OSVALDO PARAMO
Drywall Nailing 11/1/2022 Approved OSVALDO PARAMO
Final 3/3/2023 OK to Issue CofO OSVALDO PARAMO
Green Building Final 3/3/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/3/2023 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 3/3/2023 Approved OSVALDO PARAMO