3234 W MADERA AVE 90039
Certificate Information: 3234 W MADERA AVE 90039
- Application / Permit
- 20014-10000-02005
- Plan Check / Job No.
- B20LA08570
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO-STORY GROUND FLOOR ADDITION AND SECOND STORY ADDITION (953 SF TOTAL) TO EXISTING ONE-STORY SINGLE FAMILY DWELLING AT FRONT OF LOT. ALL WORK PER ENIGINEERED DESIGN.
- Permit Issued
- Issued on 6/24/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | CARLOS MONTES |
| Corrections Issued | 5/20/2020 | CARLOS MONTES |
| Quality Review Completed | 5/20/2020 | JASON HEALEY |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| Applicant returned to address corrections | 7/9/2020 | CARLOS MONTES |
| Applicant returned to address corrections | 2/4/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 4/19/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 6/16/2021 | CARLOS MONTES |
| Plan Check Approved | 6/24/2021 | CARLOS MONTES |
| Issued | 6/24/2021 | APPLICANT |
| CofO in Progress | 4/8/2022 | HAMIK HARTOUNIAN |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 1/19/2021 | MAXFIELD VERMY |
| Tenant Habitability Plan | Cleared | 3/30/2021 | PHILLIP MUNGUIA |
| Low Impact Development | Cleared | 5/20/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/26/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 6/8/2021 | STEVE MELGAR |
| Green Code | Cleared | 6/16/2021 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/18/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 8/23/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/27/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 9/1/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/4/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/18/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/15/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 11/15/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/9/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 12/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/9/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/9/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Structural Steel Frame | 12/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 12/14/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Wood Frame | 12/14/2021 | Approved | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 12/20/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/28/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 12/28/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/28/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 1/4/2022 | Corrections Issued | AMY COLIN |
| Interior/Exterior Lathing | 1/4/2022 | Not Ready for Inspection | AMY COLIN |
| BUILDING-Rough-Frame | 1/5/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Insulation | 1/5/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/5/2022 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 1/5/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 1/11/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 1/18/2022 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 1/18/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/26/2022 | Approved | AMY COLIN |
| Final | 3/31/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/31/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 3/31/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/31/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 4/6/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/6/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 4/6/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 4/6/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 4/8/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 4/8/2022 | Approved | HAMIK HARTOUNIAN |