3821 S EDGEHILL DR 90008
Certificate Information: 3821 S EDGEHILL DR 90008
- Application / Permit
- 20014-10000-01995
- Plan Check / Job No.
- B20LA08508
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW MASTER BEDROOM WITH FULL BATHROOM AND WALK-IN CLOSET AT THE REAR OF (E) SFD.
- Permit Issued
- Issued on 8/7/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2020 | CRISTINA SALAZAR |
| Corrections Issued | 5/14/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 7/21/2020 | ZAW HAN |
| Plan Check Approved | 7/27/2020 | ZAW HAN |
| Issued | 8/7/2020 | APPLICANT |
| Building Plans Picked Up | 8/7/2020 | APPLICANT |
| CofO in Progress | 10/20/2021 | ADAM ESCOTO |
| Permit Finaled | 10/22/2021 | DEROLD HAUFF |
| CofO Issued | 10/22/2021 | DEROLD HAUFF |
| Permit Finaled | 10/22/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/12/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/12/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2020 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 10/15/2020 | Approved | DONALD CRICHLOW |
| BUILDING-Rough-Frame | 11/12/2020 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 11/12/2020 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 11/12/2020 | Partial Approval | HORACE FULTZ |
| Insulation | 11/19/2020 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 3/11/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 3/11/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 3/11/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 5/3/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/3/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 5/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/13/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Partial Approval | DAVID FEILER |
| Insulation | 6/1/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/7/2021 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 6/7/2021 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 6/11/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/8/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 7/8/2021 | Approved | FREDDIE RIVERA |
| Final | 10/5/2021 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 10/5/2021 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Not Ready | HORACE FULTZ |
| Smoke Detectors | 10/5/2021 | Approved | HORACE FULTZ |
| Final | 10/13/2021 | Corrections Issued | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | ADAM ESCOTO |
| Final | 10/18/2021 | OK to Issue CofO | ADAM ESCOTO |