3931 W DE LONGPRE AVE 90027
Certificate Information: 3931 W DE LONGPRE AVE 90027
- Application / Permit
- 20014-10000-01975
- Plan Check / Job No.
- B20LA08422
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Second-story addition (741 SF) and remodel SFD (570 SF). TOTAL FLOOR AREA = 1311 SF.
- Permit Issued
- Issued on 10/7/2020
- Issuing Office
- Current Status
- CofO Issued on 4/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 6/9/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 6/15/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 8/25/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 9/3/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 9/22/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 10/1/2020 | CHUNG-WEN CHUANG |
| Issued | 10/7/2020 | APPLICANT |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| CofO in Progress | 1/25/2022 | ARTHUR SARGSYAN |
| CofO in Progress | 1/25/2022 | ARTHUR SARGSYAN |
| Permit Finaled | 4/22/2022 | DEROLD HAUFF |
| Permit Finaled | 4/22/2022 | DEROLD HAUFF |
| CofO Issued | 4/22/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/23/2020 | PATRICK MISCHLICH |
| GPI Written Notices | Cleared | 7/21/2020 | CHUNG-WEN CHUANG |
| Green Code | Cleared | 8/4/2020 | CHUNG-WEN CHUANG |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/26/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 9/1/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/2/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/31/2020 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 1/14/2021 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 2/3/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 2/9/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/9/2021 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 3/4/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 4/1/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 4/26/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 4/26/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Wood Frame | 4/26/2021 | Partial Inspection | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 5/21/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/2/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 6/2/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 6/2/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/2/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/2/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/11/2021 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 6/11/2021 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 7/1/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 7/15/2021 | Conditional Approval | JUSTIN HAWLEY |
| Shower Pan | 7/15/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/16/2021 | Partial Approval | JOSEPH MCGARRY |
| Service/Power Release | 7/16/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 7/16/2021 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 8/2/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/19/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 8/19/2021 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 9/7/2021 | Approved | JOSEPH MCGARRY |
| Gas Test | 11/1/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 11/1/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 11/1/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 1/20/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| Final | 1/21/2022 | OK to Issue CofO | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 1/21/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 1/21/2022 | Approved | ARTHUR SARGSYAN |