1504 N SCHUYLER ROAD 90210

Certificate Information: 1504 N SCHUYLER ROAD 90210

Application / Permit
20014-10000-01961
Plan Check / Job No.
B20LA08397
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION TO EXISTING TWO STORY HOME
Permit Issued
Issued on 2/1/2021
Issuing Office
Current Status
CofO Issued on 11/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 JESSE ARELLANO
Corrections Issued 6/16/2020 JESSE ARELLANO
Quality Review Completed 7/16/2020 ALLEN MANALANSAN
Applicant returned to address corrections 9/4/2020 JESSE ARELLANO
Applicant returned to address corrections 12/2/2020 JESSE ARELLANO
Applicant returned to address corrections 12/16/2020 JESSE ARELLANO
Plan Check Approved 1/25/2021 JESSE ARELLANO
Issued 2/1/2021 APPLICANT
CofO in Progress 11/6/2023 RAUL BARAJAS
CofO Issued 11/7/2023 DEROLD HAUFF
Permit Finaled 11/7/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/18/2020 TRACY TATE
BHO/Hillside ordinance Cleared 8/18/2020 TRACY TATE
BHO/Hillside ordinance Cleared 8/18/2020 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ANTHONY MAINEZ
Low Impact Development Cleared 10/3/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/13/2020 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 11/23/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 12/2/2020 JESSE ARELLANO
Green Code Cleared 12/2/2020 JESSE ARELLANO

Contact Information

Architect Smalley,, Jeffrey Marc; Lic. No.: C19163 1622 CURSON AVENUE      LOS ANGELES, CA 90046
Contractor Ecs Builders Group Inc; Lic. No.: 1035916-B 12038 TIARA ST      VALLEY VILLAGE, CA 91607

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/4/2021 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 7/1/2021 Partial Approval RICHARD STEINBACH
Wood Frame 9/30/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Conditional Approval RAUL BARAJAS
Insulation 12/10/2021 Not Ready for Inspection RAUL BARAJAS
Wood Frame 12/10/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/22/2021 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval RAUL BARAJAS
HVAC-Rough 12/22/2021 Approved RAUL BARAJAS
PLUMBING-Rough 12/22/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 1/11/2022 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 1/11/2022 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 2/14/2022 Approved RAUL BARAJAS
PLUMBING-Rough 2/14/2022 Approved RAUL BARAJAS
Insulation 2/15/2022 Approved RAUL BARAJAS
Drywall Nailing 2/24/2022 Partial Approval RAUL BARAJAS
Shower Pan 2/24/2022 Approved RAUL BARAJAS
Drywall Nailing 2/25/2022 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 3/9/2022 Approved RAUL BARAJAS
Light Gage Steel Frame 3/23/2022 Approved RAUL BARAJAS
Shower Pan 4/29/2022 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/16/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Final 12/6/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/29/2022 Approved RAUL BARAJAS
Final 12/29/2022 Corrections Issued RAUL BARAJAS
Green Building Final 12/29/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 12/29/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 12/29/2022 Approved RAUL BARAJAS
Final 10/30/2023 Conditional Approval RAUL BARAJAS
Green Building Final 10/30/2023 Approved RAUL BARAJAS