13118 W ROSE AVE 90066

Certificate Information: 13118 W ROSE AVE 90066

Application / Permit
20014-10000-01955
Plan Check / Job No.
B20LA08369
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW FRONT ADDITION (521 SF) AND NEW FRONT COVERED PORCH (153 SF) TO EXISTING 1-STORY SFD AND REMODEL EXISTING INTERIOR RESIDENCE.
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
Issued on 10/28/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 CHUNG-WEN CHUANG
Corrections Issued 6/11/2020 CHUNG-WEN CHUANG
Quality Review Completed 6/22/2020 KESETE HAREGOT
Applicant returned to address corrections 8/10/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 8/12/2020 CHUNG-WEN CHUANG
Plan Check Approved 10/19/2020 CHUNG-WEN CHUANG
Issued 10/28/2020 APPLICANT
Building Plans Picked Up 10/30/2020 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 7/13/2020 CHUNG-WEN CHUANG
Grading Pre-Inspection Cleared 7/13/2020 CHUNG-WEN CHUANG
Specific Plan Cleared 7/23/2020 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 7/28/2020 NIKTA MOUSAVI
Sewer availability Cleared 7/28/2020 NIKTA MOUSAVI
Green Code Cleared 9/17/2020 CHUNG-WEN CHUANG
Low Impact Development Cleared 10/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 10/8/2020 DINAH GARIN

Contact Information

Contractor Omni Design Studio Inc; Lic. No.: 845960-B 4245 WEST 132ND STREET SUITE A      HAWTHORNE, CA 90250
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/30/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/4/2020 Corrections Issued PIERRE VEGA
Excavation/Setback/Form/Re-Bar 11/12/2020 Approved ENRIQUE MIRELES
Insulation 11/23/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 1/8/2021 Partial Approval ENRIQUE MIRELES
ELECTRICAL-Rough 1/8/2021 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Approval ENRIQUE MIRELES
Green Building Rough 1/8/2021 Approved ENRIQUE MIRELES
HVAC-Rough 1/8/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 1/8/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 1/15/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 1/15/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 1/15/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 1/15/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 1/20/2021 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 1/20/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 1/20/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 1/28/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 1/28/2021 Approved ENRIQUE MIRELES
HVAC-Rough 1/28/2021 Approved ENRIQUE MIRELES
Insulation 1/28/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/28/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 1/28/2021 Approved ENRIQUE MIRELES
Drywall Nailing 2/2/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/2/2021 Approved ENRIQUE MIRELES
Shower Pan 2/12/2021 Approved JUAN VALENZUELA