13118 W ROSE AVE 90066
Certificate Information: 13118 W ROSE AVE 90066
- Application / Permit
- 20014-10000-01955
- Plan Check / Job No.
- B20LA08369
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW FRONT ADDITION (521 SF) AND NEW FRONT COVERED PORCH (153 SF) TO EXISTING 1-STORY SFD AND REMODEL EXISTING INTERIOR RESIDENCE.
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Current Status
- Issued on 10/28/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 6/11/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 6/22/2020 | KESETE HAREGOT |
| Applicant returned to address corrections | 8/10/2020 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 8/12/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 10/19/2020 | CHUNG-WEN CHUANG |
| Issued | 10/28/2020 | APPLICANT |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 7/13/2020 | CHUNG-WEN CHUANG |
| Grading Pre-Inspection | Cleared | 7/13/2020 | CHUNG-WEN CHUANG |
| Specific Plan | Cleared | 7/23/2020 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 7/28/2020 | NIKTA MOUSAVI |
| Green Code | Cleared | 9/17/2020 | CHUNG-WEN CHUANG |
| Low Impact Development | Cleared | 10/6/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/8/2020 | DINAH GARIN |
Contact Information
| Contractor | Omni Design Studio Inc; Lic. No.: 845960-B | 4245 WEST 132ND STREET SUITE A HAWTHORNE, CA 90250 |
| Engineer | Azarbin,, Hamid Reza; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/30/2020 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 11/4/2020 | Corrections Issued | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 11/12/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 11/23/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/8/2021 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 1/8/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 1/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/8/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/15/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/15/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 1/15/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/15/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 1/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/28/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/28/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 1/28/2021 | Approved | ENRIQUE MIRELES |
| Insulation | 1/28/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/28/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/28/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 2/2/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 2/2/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 2/12/2021 | Approved | JUAN VALENZUELA |