2250 S GUTHRIE DR 90034

Certificate Information: 2250 S GUTHRIE DR 90034

Application / Permit
20014-10000-01952
Plan Check / Job No.
B20LA08359
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL OF SFD, WITH A 2-STORY ADDITION
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 10/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2020 APPLICANT
Assigned to Plan Check Engineer 6/9/2020 CARLOS MONTES
Corrections Issued 6/11/2020 CARLOS MONTES
Quality Review Completed 6/29/2020 PRANITA SHAH
Building Plans Picked Up 7/7/2020 APPLICANT
Applicant returned to address corrections 10/27/2020 CARLOS MONTES
Plan Check Approved 11/18/2020 CARLOS MONTES
Issued 11/24/2020 APPLICANT
CofO in Progress 10/5/2022 OGANES TARAKHCHYAN
Permit Finaled 10/5/2022 DANIEL ORRANTE
CofO Issued 10/5/2022 DANIEL ORRANTE
Permit Finaled 10/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/31/2020 DINAH GARIN
Sewer availability Cleared 7/31/2020 DINAH GARIN
Low Impact Development Cleared 10/30/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/9/2020 OSCAR GUTIERREZ
GPI Written Notices Cleared 11/18/2020 CARLOS MONTES
Grading Pre-Inspection Cleared 11/18/2020 CARLOS MONTES

Contact Information

Architect Rabin,, Daniel H; Lic. No.: C36893 2323 KENILWORTH AVENUE      LOS ANGELES, CA 90039
Contractor I D C S Corporation; Lic. No.: 995061-B 485 SOUTH ROBERTSON BLVD STE 8      BEVERLY HILLS, CA 90211
Engineer Nguyen,, Tuan Minh; Lic. No.: S5883 5552 W 123RD PLACE      HAWTHORNE, CA 90250

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2021 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 2/24/2021 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 2/24/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/25/2021 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/26/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/26/2021 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 3/26/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 3/26/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/26/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/8/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 4/8/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 4/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Reinforced Masonry Frame 4/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Reinforced Concrete Frame 4/26/2021 Corrections Issued KEVIN SARGSYAN
Reinforced Masonry Frame 4/26/2021 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/28/2021 Partial Approval KEVIN SARGSYAN
Reinforced Concrete Frame 4/28/2021 Partial Approval KEVIN SARGSYAN
Reinforced Masonry Frame 4/28/2021 Partial Approval KEVIN SARGSYAN
Reinforced Masonry Frame 5/24/2021 Corrections Issued KEVIN SARGSYAN
Reinforced Concrete Frame 5/25/2021 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 5/28/2021 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval KEVIN SARGSYAN
Special/Order Compliance 7/14/2021 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 7/14/2021 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 No Access for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/7/2021 Partial Approval KEVIN SARGSYAN
HVAC-Rough 10/7/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/7/2021 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 10/18/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 10/18/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 10/18/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 10/18/2021 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 11/17/2021 Corrections Issued KEVIN SARGSYAN
Green Building Rough 11/17/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 11/17/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 11/17/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 11/17/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/23/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 12/2/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 12/8/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 12/8/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/15/2021 Partial Approval KEVIN SARGSYAN
Wood Frame 12/15/2021 Partial Approval KEVIN SARGSYAN
Insulation 12/22/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 3/3/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 4/4/2022 Approved KEVIN SARGSYAN
Drywall Nailing 4/4/2022 Approved KEVIN SARGSYAN
Green Building Rough 4/4/2022 Approved KEVIN SARGSYAN
Insulation 4/4/2022 Approved KEVIN SARGSYAN
Shower Pan 4/8/2022 Approved KEVIN SARGSYAN
Final 8/16/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 8/16/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 8/18/2022 Approved OGANES TARAKHCHYAN
Service/Power Release 8/18/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 9/6/2022 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/6/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 9/6/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 9/6/2022 Approved OGANES TARAKHCHYAN
Final 9/14/2022 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 9/14/2022 Approved ANDREW NAVE
Gas Test 9/14/2022 Approved ANDREW NAVE
Green Building Final 9/14/2022 Corrections Issued ANDREW NAVE
METHANE-Barrier 9/14/2022 Approved ANDREW NAVE
METHANE-Subgrade 9/14/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Not Ready ANDREW NAVE
Service/Power Release 9/14/2022 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 9/14/2022 Corrections Issued ANDREW NAVE
Final 10/3/2022 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 10/3/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 10/3/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 10/3/2022 Approved OGANES TARAKHCHYAN